Kitchen · domestic · fixed price
Job 3942
CompleteKitchen fit-out
For Stuart Thornton, Chew Magna. Crew A with Kate Lyons. On site 5 Jan to 15 Jan, handed over 21 Jan 2026.
Agreed price
£25,850
ex VAT, +£1,040 extras billed
Final margin
26.9%
quoted 25.7%
100% of the work done17 cabinets
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
CostEstimateActual so farFinalDifference
Labour216 h logged against 195.5 h estimated, at each person's true cost rate£5,506£5,952£5,952+£4468.1% overMaterials6 purchases received£10,550£10,543£10,543-£70.1% underSubcontract5 invoices from the electrician, plumber and plasterer£3,150£3,150£3,150On budgetTotal cost£19,206£19,645£19,645+£4392.3% overExtras captured on site
1 extra on this job
Quoted margin25.7%£6,644 on £25,850
Final margin26.9%£7,245 profit
Invoiced so far£26,890of £26,890, £26,890 paid
Where the money went
| Person | Hours | Labour cost | Difference |
|---|---|---|---|
SR Steve Rowe Lead fitter, crew A, £34/h at cost | 72 h of 68.5 h estimated | £2,448 of £2,329 | +£119 |
LD Liam Doyle Joiner, crew A, £30/h at cost | 72 h of 68.5 h estimated | £2,160 of £2,055 | +£105 |
JP Josh Penrose Apprentice joiner, crew A, £16/h at cost | 56 h of 43 h estimated | £896 of £688 | +£208 |
RF Rob Finch Decorator, £28/h at cost | 16 h of 15.5 h estimated | £448 of £434 | +£14 |
True labour cost. The 15 kitchens finished this year really took 12.95 h per cabinet, against the old rule of 11.5. This job: 17 cabinets, priced on 195.5 h. Rule of thumb: 11.5 h per cabinet. New quotes now use the true rate →
| Estimate line | Estimate | Ordered | Received | Difference |
|---|---|---|---|---|
Kitchen units and doors Wrenfold Kitchen Supply, PO-5101 | £6,120 | £6,027 | £6,027 | -£93 |
Worktops, templated and fitted Halbrook Worktops, PO-5109 | £2,850 | £2,927 | £2,927 | +£77 |
Plaster, board and sundries Avonmere Builders Merchants, PO-5115 | £420 | £428 | £428 | +£8 |
Timber, panels and fixings Kestle Timber, PO-5110 | £320 | £313 | £313 | -£7 |
Lighting and electrical fittings Voltmere Electrical Wholesale, PO-5116 | £420 | £425 | £425 | +£5 |
Splashback tiles and adhesive Brackwell Tiles, PO-5120 | £420 | £423 | £423 | +£3 |
Materials count when they are delivered and signed for on site. Nothing is on order and not received. Supplier bills post to Xero from here.
| Trade | Agreed | Invoiced | Difference |
|---|---|---|---|
Electrics Gary Pullen Electrical, 2 invoices | £1,420 | £1,420 | on the agreed price |
Plumbing Jon Haskins Plumbing and Heating, 2 invoices | £1,040 | £1,040 | on the agreed price |
Plastering Mark Dent Plastering, 1 invoice | £690 | £690 | on the agreed price |
The forecast counts each trade at its agreed price until it invoices more.
Agreed price
stage invoices at 25%, 50% and 25%
£25,850.00
Extras billed
V-3942-1
£1,040.00
Revenue
£26,890.00
Labour
final
- £5,952.00
Materials
final
- £10,543.26
Subcontract
final
- £3,150.00
Profit
26.9% margin, quoted at 25.7% (£6,644)
£7,244.74
Cost week by week
£19,645 spent over 3 weeks, against a £19,206 estimate
LabourMaterialsSubcontract
| Week of | Hours | Labour | Materials | Subcontract | Total |
|---|---|---|---|---|---|
| 29 Dec 2025 | 0 h | £0 | £6,027 | £0 | £6,027 |
| 5 Jan | 112 h | £3,072 | £1,588 | £1,920 | £6,580 |
| 12 Jan | 104 h | £2,880 | £2,927 | £1,230 | £7,037 |
Extras and variations · 1
Variations →Timesheets · 216 h, £5,952 at cost
Timesheets →| Week of | Person | Hours | Cost | Status |
|---|---|---|---|---|
| 12 Jan Tap for the days Mon 12 Jan8 hTS-00052 Tue 13 Jan8 hTS-00058 Thu 15 Jan8 hTS-00070 | JPJosh Penrose | 24 h 3 days | £384.00 at £16/h | approved from the paper sheets |
| 12 Jan Tap for the days Mon 12 Jan8 hTS-00053 Tue 13 Jan8 hTS-00059 Wed 14 Jan8 hTS-00063 Thu 15 Jan8 hTS-00071 | LDLiam Doyle | 32 h 4 days | £960.00 at £30/h | approved from the paper sheets |
| 12 Jan Tap for the days Wed 14 Jan8 hTS-00064 Thu 15 Jan8 hTS-00073 | RFRob Finch | 16 h 2 days | £448.00 at £28/h | approved from the paper sheets |
| 12 Jan Tap for the days Mon 12 Jan8 hTS-00054 Tue 13 Jan8 hTS-00060 Wed 14 Jan8 hTS-00065 Thu 15 Jan8 hTS-00075 | SRSteve Rowe | 32 h 4 days | £1,088.00 at £34/h | approved from the paper sheets |
| 5 Jan Tap for the days Mon 5 Jan8 hTS-00005 Tue 6 Jan8 hTS-00016 Thu 8 Jan8 hTS-00034 Fri 9 Jan8 hTS-00044 | JPJosh Penrose | 32 h 4 days | £512.00 at £16/h | approved from the paper sheets |
| 5 Jan Tap for the days Mon 5 Jan8 hTS-00006 Tue 6 Jan8 hTS-00017 Wed 7 Jan8 hTS-00025 Thu 8 Jan8 hTS-00035 Fri 9 Jan8 hTS-00045 | LDLiam Doyle | 40 h 5 days | £1,200.00 at £30/h | approved from the paper sheets |
| 5 Jan Tap for the days Mon 5 Jan8 hTS-00010 Tue 6 Jan8 hTS-00021 Wed 7 Jan8 hTS-00029 Thu 8 Jan8 hTS-00039 Fri 9 Jan8 hTS-00048 | SRSteve Rowe | 40 h 5 days | £1,360.00 at £34/h | approved from the paper sheets |
Purchases · 6, £10,543
Purchases →| Order | What | Status | Net |
|---|---|---|---|
| PO-5120 Brackwell Tiles, raised 3 Jan | Splashback tiles and adhesive | Delivered 8 Jan, billed | £422.81 |
| PO-5115 Avonmere Builders Merchants, raised 2 Jan | Plaster, board and sundries | Delivered 5 Jan, billed | £427.54 |
| PO-5116 Voltmere Electrical Wholesale, raised 2 Jan | Lighting and electrical fittings | Delivered 5 Jan, billed | £425.28 |
| PO-5109 Halbrook Worktops, raised 1 Jan | Worktops, templated and fitted | Delivered 13 Jan, billed | £2,927.45 |
| PO-5110 Kestle Timber, raised 1 Jan | Timber, panels and fixings | Delivered 5 Jan, billed | £312.76 |
| PO-5101 Wrenfold Kitchen Supply, raised 11 Dec 2025 | Kitchen units and doors | Delivered 2 Jan, billed | £6,027.42 |
Subcontractor invoices · 5, £3,150
Tap one for the subcontractor| Invoice | Work | Status | Amount |
|---|---|---|---|
| SC-3413 Gary Pullen Electrical, 15 Jan | Electrics, second fix | Paid | £710.00 |
Gary Pullen ElectricalElectrician, Kingswood. Day rate £260. Insured to Mar 2027. Domestic jobs. Part P registered. | |||
| SC-3414 Jon Haskins Plumbing and Heating, 15 Jan | Plumbing, second fix | Paid | £520.00 |
Jon Haskins Plumbing and HeatingPlumber, Bedminster. Day rate £250. Insured to May 2027. Gas Safe registered. | |||
| SC-3409 Mark Dent Plastering, 8 Jan | Plastering, skim and making good | Paid | £690.00 |
Mark Dent PlasteringPlasterer, Brislington. Day rate £220. Insured to Feb 2027. Skim and dry-lining. | |||
| SC-3404 Gary Pullen Electrical, 6 Jan | Electrics, first fix | Paid | £710.00 |
Gary Pullen ElectricalElectrician, Kingswood. Day rate £260. Insured to Mar 2027. Domestic jobs. Part P registered. | |||
| SC-3405 Jon Haskins Plumbing and Heating, 6 Jan | Plumbing, first fix | Paid | £520.00 |
Jon Haskins Plumbing and HeatingPlumber, Bedminster. Day rate £250. Insured to May 2027. Gas Safe registered. | |||
Invoices · posted to Xero when sent
Billing →| Invoice | Stage | Status | Net | Gross | Xero |
|---|---|---|---|---|---|
| INV-2202 issued 26 Nov 2025 | Deposit 1 line | Paid 5 Dec 2025 | £6,462.50 | £7,755.00 | posted |
| INV-2217 issued 12 Jan | Progress 1 line | Paid 19 Jan | £12,925.00 | £15,510.00 | posted |
| INV-2227 issued 22 Jan | Completion 2 lines, with V-3942-1 | Paid 3 Feb | £7,502.50 | £9,003.00 | posted |
Stages £25,850 + billed extras £1,040 = £26,890 on invoices. £26,890 sent, £26,890 paid.
Client
Client page →Stuart Thornton
Stuart Thornton · client since 6 Nov 2025
Site39 Kingsley Road, Chew Magna
Phone07700 900632
PortalLive: progress, extras, invoices
Messages in the portal
No messages on this job yet.
People and dates
Project managerKate Lyons
CrewCrew A: Steve, Liam, Josh
Booked24 Nov 2025
StartedMon 5 Jan
Handed over21 Jan 2026
Timeline
Handed over and closed
Kate · 21 Jan 15:00
Gary Pullen Electrical: Electrics, second fix, £710.00
Gary Pullen · 15 Jan 17:00
Jon Haskins Plumbing and Heating: Plumbing, second fix, £520.00
Jon Haskins · 15 Jan 17:00
Delivered: Worktops, templated and fitted from Halbrook Worktops (PO-5109, £2,927.45)
Steve Rowe · 13 Jan 08:15
V-3942-1 approved by the client (email), £1,040
Client · 8 Jan 19:00
Mark Dent Plastering: Plastering, skim and making good, £690.00
Mark Dent · 8 Jan 17:00
Delivered: Splashback tiles and adhesive from Brackwell Tiles (PO-5120, £422.81)
Steve Rowe · 8 Jan 08:15
Extra captured: Pull-out bin unit
Steve · 7 Jan 11:30
Gary Pullen Electrical: Electrics, first fix, £710.00
Gary Pullen · 6 Jan 17:00
Jon Haskins Plumbing and Heating: Plumbing, first fix, £520.00
Jon Haskins · 6 Jan 17:00
Delivered: Timber, panels and fixings from Kestle Timber (PO-5110, £312.76)
Steve Rowe · 5 Jan 08:15
Delivered: Plaster, board and sundries from Avonmere Builders Merchants (PO-5115, £427.54)
Steve Rowe · 5 Jan 08:15
First day on site: Josh, Liam, Steve
Site app · 5 Jan 07:30
Delivered: Kitchen units and doors from Wrenfold Kitchen Supply (PO-5101, £6,027.42)
Steve Rowe · 2 Jan 08:15
Deposit invoice INV-2202 sent and posted to Xero, £6,462.50 ex VAT; paid 5 Dec 2025
Auto · 26 Nov 2025 16:00
Booked: £25,850 ex VAT
Owen · 24 Nov 2025 11:00