LIVE DEMO
Kitchen · domestic · fixed price

Job 3944

Complete
Kitchen fit-out
For Beth and Philip Osborne, Bath. Crew A with Kate Lyons. On site 19 Jan to 26 Jan, handed over 31 Jan 2026.
Agreed price
£17,500
ex VAT
Final margin
22.1%
quoted 25.6%
100% of the work done11 cabinets
Client's portal view
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
Quoted margin25.6%£4,474 on £17,500
Final margin22.1%£3,859 profit
Invoiced so far£17,500of £17,500, £17,500 paid
Where the money went
PersonHoursLabour costDifference
SR
Steve Rowe
Lead fitter, crew A, £34/h at cost
48 h
of 44.5 h estimated
£1,632
of £1,513
+£119
LD
Liam Doyle
Joiner, crew A, £30/h at cost
48 h
of 44.5 h estimated
£1,440
of £1,335
+£105
JP
Josh Penrose
Apprentice joiner, crew A, £16/h at cost
40 h
of 28 h estimated
£640
of £448
+£192
RF
Rob Finch
Decorator, £28/h at cost
8 h
of 10 h estimated
£224
of £280
-£56
True labour cost. The 15 kitchens finished this year really took 12.95 h per cabinet, against the old rule of 11.5. This job: 11 cabinets, priced on 127 h. Rule of thumb: 11.5 h per cabinet. New quotes now use the true rate →
Cost week by week
£13,641 spent over 3 weeks, against a £13,026 estimate
LabourMaterialsSubcontract
Extras and variations · 0
Variations →
No extras on this job.
Timesheets · 144 h, £3,936 at cost
Timesheets →
Week ofPersonHoursCostStatus
26 Jan
Tap for the days
JPJosh Penrose8 h
1 day
£128.00
at £16/h
approved
from the paper sheets
26 Jan
Tap for the days
LDLiam Doyle8 h
1 day
£240.00
at £30/h
approved
from the paper sheets
26 Jan
Tap for the days
RFRob Finch8 h
1 day
£224.00
at £28/h
approved
from the paper sheets
26 Jan
Tap for the days
SRSteve Rowe8 h
1 day
£272.00
at £34/h
approved
from the paper sheets
19 Jan
Tap for the days
JPJosh Penrose32 h
4 days
£512.00
at £16/h
approved
from the paper sheets
19 Jan
Tap for the days
LDLiam Doyle40 h
5 days
£1,200.00
at £30/h
approved
from the paper sheets
19 Jan
Tap for the days
SRSteve Rowe40 h
5 days
£1,360.00
at £34/h
approved
from the paper sheets
Purchases · 6, £7,055
Purchases →
OrderWhatStatusNet
PO-5134
Brackwell Tiles, raised 16 Jan
Splashback tiles and adhesiveDelivered 21 Jan, billed£284.96
PO-5135
Voltmere Electrical Wholesale, raised 16 Jan
Lighting and electrical fittingsDelivered 19 Jan, billed£279.51
PO-5136
Avonmere Builders Merchants, raised 16 Jan
Plaster, board and sundriesDelivered 19 Jan, billed£278.71
PO-5133
Kestle Timber, raised 15 Jan
Timber, panels and fixingsDelivered 19 Jan, billed£213.31
PO-5126
Halbrook Worktops, raised 11 Jan
Worktops, templated and fittedDelivered 23 Jan, billed£1,892.88
PO-5104
Wrenfold Kitchen Supply, raised 25 Dec 2025
Kitchen units and doorsDelivered 16 Jan, billed£4,105.36
Subcontractor invoices · 5, £2,650
Tap one for the subcontractor
InvoiceWorkStatusAmount
SC-3433
Gary Pullen Electrical, 26 Jan
Electrics, second fixPaid£595.00
SC-3434
Jon Haskins Plumbing and Heating, 26 Jan
Plumbing, second fixPaid£435.00
SC-3427
Mark Dent Plastering, 21 Jan
Plastering, skim and making goodPaid£590.00
SC-3424
Jon Haskins Plumbing and Heating, 20 Jan
Plumbing, first fixPaid£435.00
SC-3419
Gary Pullen Electrical, 19 Jan
Electrics, first fixPaid£595.00
Invoices · posted to Xero when sent
Billing →
InvoiceStageStatusNetGrossXero
INV-2204
issued 8 Dec 2025
Deposit
1 line
Paid 14 Dec 2025£4,375.00£5,250.00posted
INV-2228
issued 22 Jan
Progress
1 line
Paid 3 Feb£8,750.00£10,500.00posted
INV-2237
issued 2 Feb
Completion
1 line
Paid 8 Feb£4,375.00£5,250.00posted
Stages £17,500 + billed extras £0 = £17,500 on invoices. £17,500 sent, £17,500 paid.
BP
Beth and Philip Osborne
Beth Osborne · client since 20 Nov 2025
Site86 Kingsley Road, Bath
Phone07700 900954
PortalLive: progress, extras, invoices
See what Beth sees in the portal
Messages in the portal
No messages on this job yet.
People and dates
Project managerKate Lyons
CrewCrew A: Steve, Liam, Josh
Booked6 Dec 2025
StartedMon 19 Jan
Handed over31 Jan 2026
Timeline
Handed over and closed
Kate · 31 Jan 15:00
Gary Pullen Electrical: Electrics, second fix, £595.00
Gary Pullen · 26 Jan 17:00
Jon Haskins Plumbing and Heating: Plumbing, second fix, £435.00
Jon Haskins · 26 Jan 17:00
Mark Dent Plastering: Plastering, skim and making good, £590.00
Mark Dent · 21 Jan 17:00
Jon Haskins Plumbing and Heating: Plumbing, first fix, £435.00
Jon Haskins · 20 Jan 17:00
Gary Pullen Electrical: Electrics, first fix, £595.00
Gary Pullen · 19 Jan 17:00
First day on site: Josh, Liam, Steve
Site app · 19 Jan 07:30
Booked: £17,500 ex VAT
Owen · 6 Dec 2025 11:00