Bathroom · domestic · fixed price

Job 3954

Complete
En-suite shower room
For Laura Rossiter, Clifton. Crew B with Kate Lyons. On site 9 Feb to 11 Feb, handed over 14 Feb 2026.
Agreed price
£9,400
ex VAT
Final margin
22.0%
quoted 23.2%
100% of the work done15 m² tiled
Client's portal view
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
Quoted margin23.2%£2,184 on £9,400
Final margin22.0%£2,065 profit
Invoiced so far£9,400of £9,400, £9,400 paid
Where the money went
PersonHoursLabour costDifference
MT
Mike Tanner
Lead fitter and tiler, crew B, £34/h at cost
24 h
of 25 h estimated
£816
of £850
-£34
RH
Ryan Hale
Fitter, crew B, £30/h at cost
24 h
of 22 h estimated
£720
of £660
+£60
CW
Callum Webb
Apprentice fitter, crew B, £16/h at cost
16 h
of 16 h estimated
£256
of £256
on budget
True labour cost. The 25 bathrooms finished this year really took 4.5 h per m² tiled, against the old rule of 4.2. This job: 15 m² tiled, priced on 63 h. Rule of thumb: 4.2 h per m² tiled. New quotes now use the true rate →
Cost week by week
£7,335 spent over 2 weeks, against a £7,216 estimate
LabourMaterialsSubcontract
Extras and variations · 0
Variations →
No extras on this job.
Timesheets · 64 h, £1,792 at cost
Timesheets →
Week ofPersonHoursCostStatus
9 Feb
Tap for the days
CWCallum Webb16 h
2 days
£256.00
at £16/h
approved
from the paper sheets
9 Feb
Tap for the days
MTMike Tanner24 h
3 days
£816.00
at £34/h
approved
from the paper sheets
9 Feb
Tap for the days
RHRyan Hale24 h
3 days
£720.00
at £30/h
approved
from the paper sheets
Purchases · 5, £3,500
Purchases →
OrderWhatStatusNet
PO-5165
Avonmere Builders Merchants, raised 6 Feb
Board, tanking and sundriesDelivered 9 Feb, billed£463.64
PO-5166
Voltmere Electrical Wholesale, raised 6 Feb
Lighting and extractorDelivered 9 Feb, billed£186.38
PO-5163
Brackwell Tiles, raised 5 Feb
Wall and floor tiles, adhesive, groutDelivered 10 Feb, billed£935.54
PO-5164
Kestle Timber, raised 5 Feb
Timber and fixingsDelivered 9 Feb, billed£237.76
PO-5157
Linmouth Bathroom Supply, raised 28 Jan
Sanitaryware and brasswareDelivered 6 Feb, billed£1,676.20
Subcontractor invoices · 5, £2,044
Tap one for the subcontractor
InvoiceWorkStatusAmount
SC-3459
Jon Haskins Plumbing and Heating, 11 Feb
Plumbing, second fixPaid£634.04
SC-3460
Gary Pullen Electrical, 11 Feb
Electrics, second fixPaid£183.40
SC-3456
Mark Dent Plastering, 10 Feb
Plastering, skim and making goodPaid£408.72
SC-3452
Jon Haskins Plumbing and Heating, 9 Feb
Plumbing, first fixPaid£634.04
SC-3453
Gary Pullen Electrical, 9 Feb
Electrics, first fixPaid£183.40
Invoices · posted to Xero when sent
Billing →
InvoiceStageStatusNetGrossXero
INV-2215
issued 6 Jan
Deposit
1 line
Paid 11 Jan£2,350.00£2,820.00posted
INV-2247
issued 10 Feb
Progress
1 line
Paid 19 Feb£4,700.00£5,640.00posted
INV-2248
issued 16 Feb
Completion
1 line
Paid 22 Feb£2,350.00£2,820.00posted
Stages £9,400 + billed extras £0 = £9,400 on invoices. £9,400 sent, £9,400 paid.
LR
Laura Rossiter
Laura Rossiter · client since 11 Dec 2025
Site76 Rowan Drive, Clifton
Phone07700 900134
PortalLive: progress, extras, invoices
See what Laura sees in the portal
Messages in the portal
No messages on this job yet.
People and dates
Project managerKate Lyons
CrewCrew B: Mike, Ryan, Callum
Booked4 Jan 2026
StartedMon 9 Feb
Handed over14 Feb 2026
Timeline
Handed over and closed
Kate · 14 Feb 15:00
Jon Haskins Plumbing and Heating: Plumbing, second fix, £634.04
Jon Haskins · 11 Feb 17:00
Gary Pullen Electrical: Electrics, second fix, £183.40
Gary Pullen · 11 Feb 17:00
Mark Dent Plastering: Plastering, skim and making good, £408.72
Mark Dent · 10 Feb 17:00
Jon Haskins Plumbing and Heating: Plumbing, first fix, £634.04
Jon Haskins · 9 Feb 17:00
Gary Pullen Electrical: Electrics, first fix, £183.40
Gary Pullen · 9 Feb 17:00
First day on site: Callum, Mike, Ryan
Site app · 9 Feb 07:30
Booked: £9,400 ex VAT
Owen · 4 Jan 11:00