LIVE DEMO
Kitchen · domestic · fixed price

Job 3957

Complete
Kitchen fit-out
For Sarah and Peter Gane, Southville. Crew A with Kate Lyons. On site 3 Mar to 9 Mar, handed over 14 Mar 2026.
Agreed price
£14,600
ex VAT, +£710 extras billed
Final margin
25.6%
quoted 24.9%
100% of the work done9 cabinets
Client's portal view
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
Extras captured on site
1 extra on this job
Every extra ↓
Quoted margin24.9%£3,640 on £14,600
Final margin25.6%£3,915 profit
Invoiced so far£15,310of £15,310, £15,310 paid
Where the money went
PersonHoursLabour costDifference
SR
Steve Rowe
Lead fitter, crew A, £34/h at cost
40 h
of 36 h estimated
£1,360
of £1,224
+£136
LD
Liam Doyle
Joiner, crew A, £30/h at cost
40 h
of 36 h estimated
£1,200
of £1,080
+£120
JP
Josh Penrose
Apprentice joiner, crew A, £16/h at cost
32 h
of 23 h estimated
£512
of £368
+£144
RF
Rob Finch
Decorator, £28/h at cost
8 h
of 8.5 h estimated
£224
of £238
-£14
True labour cost. The 15 kitchens finished this year really took 12.95 h per cabinet, against the old rule of 11.5. This job: 9 cabinets, priced on 103.5 h. Rule of thumb: 11.5 h per cabinet. New quotes now use the true rate →
Cost week by week
£11,395 spent over 2 weeks, against a £10,960 estimate
LabourMaterialsSubcontract
Extras and variations · 1
Variations →
Timesheets · 120 h, £3,296 at cost
Timesheets →
Week ofPersonHoursCostStatus
9 Mar
Tap for the days
JPJosh Penrose8 h
1 day
£128.00
at £16/h
approved
from the paper sheets
9 Mar
Tap for the days
LDLiam Doyle8 h
1 day
£240.00
at £30/h
approved
from the paper sheets
9 Mar
Tap for the days
RFRob Finch8 h
1 day
£224.00
at £28/h
approved
from the paper sheets
9 Mar
Tap for the days
SRSteve Rowe8 h
1 day
£272.00
at £34/h
approved
from the paper sheets
2 Mar
Tap for the days
JPJosh Penrose24 h
3 days
£384.00
at £16/h
approved
from the paper sheets
2 Mar
Tap for the days
LDLiam Doyle32 h
4 days
£960.00
at £30/h
approved
from the paper sheets
2 Mar
Tap for the days
SRSteve Rowe32 h
4 days
£1,088.00
at £34/h
approved
from the paper sheets
Purchases · 6, £5,649
Purchases →
OrderWhatStatusNet
PO-5200
Brackwell Tiles, raised 28 Feb
Splashback tiles and adhesiveDelivered 5 Mar, billed£227.72
PO-5201
Voltmere Electrical Wholesale, raised 28 Feb
Lighting and electrical fittingsDelivered 3 Mar, billed£214.94
PO-5202
Avonmere Builders Merchants, raised 28 Feb
Plaster, board and sundriesDelivered 3 Mar, billed£215.82
PO-5199
Kestle Timber, raised 27 Feb
Timber, panels and fixingsDelivered 3 Mar, billed£172.03
PO-5189
Halbrook Worktops, raised 22 Feb
Worktops, templated and fittedDelivered 6 Mar, billed£1,526.63
PO-5169
Wrenfold Kitchen Supply, raised 8 Feb
Kitchen units and doorsDelivered 2 Mar, billed£3,292.01
Subcontractor invoices · 5, £2,450
Tap one for the subcontractor
InvoiceWorkStatusAmount
SC-3491
Gary Pullen Electrical, 9 Mar
Electrics, second fixPaid£550.00
SC-3492
Jon Haskins Plumbing and Heating, 9 Mar
Plumbing, second fixPaid£405.00
SC-3488
Mark Dent Plastering, 5 Mar
Plastering, skim and making goodPaid£540.00
SC-3487
Jon Haskins Plumbing and Heating, 4 Mar
Plumbing, first fixPaid£405.00
SC-3485
Gary Pullen Electrical, 3 Mar
Electrics, first fixPaid£550.00
Invoices · posted to Xero when sent
Billing →
InvoiceStageStatusNetGrossXero
INV-2225
issued 19 Jan
Deposit
1 line
Paid 24 Jan£3,650.00£4,380.00posted
INV-2266
issued 6 Mar
Progress
1 line
Paid 19 Mar£7,300.00£8,760.00posted
INV-2274
issued 16 Mar
Completion
2 lines, with V-3957-1
Paid 24 Mar£4,360.00£5,232.00posted
Stages £14,600 + billed extras £710 = £15,310 on invoices. £15,310 sent, £15,310 paid.
SP
Sarah and Peter Gane
Sarah Gane · client since 2 Jan 2026
Site72 Chestnut Walk, Southville
Phone07700 900640
PortalLive: progress, extras, invoices
See what Sarah sees in the portal
Messages in the portal
No messages on this job yet.
People and dates
Project managerKate Lyons
CrewCrew A: Steve, Liam, Josh
Booked17 Jan 2026
StartedTue 3 Mar
Handed over14 Mar 2026
Timeline
Handed over and closed
Kate · 14 Mar 15:00
Gary Pullen Electrical: Electrics, second fix, £550.00
Gary Pullen · 9 Mar 17:00
Jon Haskins Plumbing and Heating: Plumbing, second fix, £405.00
Jon Haskins · 9 Mar 17:00
Mark Dent Plastering: Plastering, skim and making good, £540.00
Mark Dent · 5 Mar 17:00
Jon Haskins Plumbing and Heating: Plumbing, first fix, £405.00
Jon Haskins · 4 Mar 17:00
Gary Pullen Electrical: Electrics, first fix, £550.00
Gary Pullen · 3 Mar 17:00
First day on site: Josh, Liam, Steve
Site app · 3 Mar 07:30
Booked: £14,600 ex VAT
Owen · 17 Jan 11:00