Kitchen · domestic · fixed price

Job 3964

Complete
Kitchen fit-out
For Alison and Matthew Mallett, Bishopston. Crew A with Kate Lyons. On site 25 Mar to 8 Apr, handed over 16 Apr 2026.
Agreed price
£21,950
ex VAT
Final margin
21.8%
quoted 26.4%
100% of the work done14 cabinets
Client's portal view
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
Quoted margin26.4%£5,802 on £21,950
Final margin21.8%£4,778 profit
Invoiced so far£21,950of £21,950, £21,950 paid
Where the money went
PersonHoursLabour costDifference
SR
Steve Rowe
Lead fitter, crew A, £34/h at cost
64 h
of 56.5 h estimated
£2,176
of £1,921
+£255
LD
Liam Doyle
Joiner, crew A, £30/h at cost
64 h
of 56.5 h estimated
£1,920
of £1,695
+£225
JP
Josh Penrose
Apprentice joiner, crew A, £16/h at cost
48 h
of 35.5 h estimated
£768
of £568
+£200
RF
Rob Finch
Decorator, £28/h at cost
16 h
of 13 h estimated
£448
of £364
+£84
True labour cost. The 15 kitchens finished this year really took 12.95 h per cabinet, against the old rule of 11.5. This job: 14 cabinets, priced on 161.5 h. Rule of thumb: 11.5 h per cabinet. New quotes now use the true rate →
Cost week by week
£17,172 spent over 3 weeks, against a £16,148 estimate
LabourMaterialsSubcontract
Extras and variations · 0
Variations →
No extras on this job.
Timesheets · 192 h, £5,312 at cost
Timesheets →
Week ofPersonHoursCostStatus
6 Apr
Tap for the days
JPJosh Penrose8 h
1 day
£128.00
at £16/h
approved
from the paper sheets
6 Apr
Tap for the days
LDLiam Doyle8 h
1 day
£240.00
at £30/h
approved
from the paper sheets
6 Apr
Tap for the days
RFRob Finch16 h
2 days
£448.00
at £28/h
approved
from the paper sheets
6 Apr
Tap for the days
SRSteve Rowe8 h
1 day
£272.00
at £34/h
approved
from the paper sheets
30 Mar
Tap for the days
JPJosh Penrose24 h
3 days
£384.00
at £16/h
approved
from the paper sheets
30 Mar
Tap for the days
LDLiam Doyle32 h
4 days
£960.00
at £30/h
approved
from the paper sheets
30 Mar
Tap for the days
SRSteve Rowe32 h
4 days
£1,088.00
at £34/h
approved
from the paper sheets
23 Mar
Tap for the days
JPJosh Penrose16 h
2 days
£256.00
at £16/h
approved
from the paper sheets
23 Mar
Tap for the days
LDLiam Doyle24 h
3 days
£720.00
at £30/h
approved
from the paper sheets
23 Mar
Tap for the days
SRSteve Rowe24 h
3 days
£816.00
at £34/h
approved
from the paper sheets
Purchases · 6, £8,737
Purchases →
OrderWhatStatusNet
PO-5234
Brackwell Tiles, raised 25 Mar
Splashback tiles and adhesiveDelivered 30 Mar, billed£330.74
PO-5232
Voltmere Electrical Wholesale, raised 22 Mar
Lighting and electrical fittingsDelivered 25 Mar, billed£355.82
PO-5233
Avonmere Builders Merchants, raised 22 Mar
Plaster, board and sundriesDelivered 25 Mar, billed£343.38
PO-5229
Kestle Timber, raised 21 Mar
Timber, panels and fixingsDelivered 25 Mar, billed£260.82
PO-5231
Halbrook Worktops, raised 21 Mar
Worktops, templated and fittedDelivered 2 Apr, billed£2,330.25
PO-5204
Wrenfold Kitchen Supply, raised 2 Mar
Kitchen units and doorsDelivered 24 Mar, billed£5,115.97
Subcontractor invoices · 5, £3,123
Tap one for the subcontractor
InvoiceWorkStatusAmount
SC-3527
Gary Pullen Electrical, 8 Apr
Electrics, second fixPaid£705.43
SC-3528
Jon Haskins Plumbing and Heating, 8 Apr
Plumbing, second fixPaid£516.96
SC-3520
Mark Dent Plastering, 30 Mar
Plastering, skim and making goodPaid£678.51
SC-3516
Gary Pullen Electrical, 26 Mar
Electrics, first fixPaid£705.44
SC-3517
Jon Haskins Plumbing and Heating, 26 Mar
Plumbing, first fixPaid£516.96
Invoices · posted to Xero when sent
Billing →
InvoiceStageStatusNetGrossXero
INV-2246
issued 9 Feb
Deposit
1 line
Paid 14 Feb£5,487.50£6,585.00posted
INV-2288
issued 1 Apr
Progress
1 line
Paid 15 Apr£10,975.00£13,170.00posted
INV-2299
issued 17 Apr
Completion
1 line
Paid 29 Apr£5,487.50£6,585.00posted
Stages £21,950 + billed extras £0 = £21,950 on invoices. £21,950 sent, £21,950 paid.
AM
Alison and Matthew Mallett
Alison Mallett · client since 24 Jan 2026
Site12 Mill Lane, Bishopston
Phone07700 900626
PortalLive: progress, extras, invoices
See what Alison sees in the portal
Messages in the portal
No messages on this job yet.
People and dates
Project managerKate Lyons
CrewCrew A: Steve, Liam, Josh
Booked5 Feb 2026
StartedWed 25 Mar
Handed over16 Apr 2026
Timeline
Handed over and closed
Kate · 16 Apr 15:00
Gary Pullen Electrical: Electrics, second fix, £705.43
Gary Pullen · 8 Apr 17:00
Jon Haskins Plumbing and Heating: Plumbing, second fix, £516.96
Jon Haskins · 8 Apr 17:00
Mark Dent Plastering: Plastering, skim and making good, £678.51
Mark Dent · 30 Mar 17:00
Gary Pullen Electrical: Electrics, first fix, £705.44
Gary Pullen · 26 Mar 17:00
Jon Haskins Plumbing and Heating: Plumbing, first fix, £516.96
Jon Haskins · 26 Mar 17:00
First day on site: Liam, Steve
Site app · 25 Mar 07:30
Booked: £21,950 ex VAT