LIVE DEMO
Bathroom · domestic · fixed price

Job 3979

Complete
Cloakroom and utility refit
For Hannah and James Vickery, Southville. Chris Moss (small works) with Kate Lyons. On site 30 Apr to 7 May, handed over 14 May 2026.
Agreed price
£9,800
ex VAT
Final margin
26.9%
quoted 30.2%
100% of the work done7 m²
Client's portal view
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
Quoted margin30.2%£2,958 on £9,800
Final margin26.9%£2,636 profit
Invoiced so far£9,800of £9,800, £9,800 paid
Where the money went
PersonHoursLabour costDifference
CM
Chris Moss
Small works and snagging fitter, £30/h at cost
40 h
of 33.5 h estimated
£1,200
of £1,005
+£195
SK
Sam Kerridge
Labourer and driver, £22/h at cost
8 h
of 8.5 h estimated
£176
of £187
-£11
Rule of thumb: 6 h per m².
Cost week by week
£7,164 spent over 2 weeks, against a £6,842 estimate
LabourMaterialsSubcontract
Extras and variations · 0
Variations →
No extras on this job.
Timesheets · 48 h, £1,376 at cost
Timesheets →
Week ofPersonHoursCostStatus
4 May
Tap for the days
CMChris Moss24 h
3 days
£720.00
at £30/h
approved
from the paper sheets
27 Apr
Tap for the days
CMChris Moss16 h
2 days
£480.00
at £30/h
approved
from the paper sheets
27 Apr
Tap for the days
SKSam Kerridge8 h
1 day
£176.00
at £22/h
approved
from the paper sheets
Purchases · 4, £4,388
Purchases →
OrderWhatStatusNet
PO-5283
Brackwell Tiles, raised 30 Apr
Tiles and adhesiveDelivered 5 May, billed£665.03
PO-5280
Avonmere Builders Merchants, raised 27 Apr
Board and sundriesDelivered 30 Apr, billed£426.83
PO-5271
Linmouth Bathroom Supply, raised 20 Apr
Sanitaryware and brasswareDelivered 29 Apr, billed£2,194.30
PO-5261
Wrenfold Kitchen Supply, raised 14 Apr
Utility unitsDelivered 30 Apr, billed£1,102.32
Subcontractor invoices · 4, £1,400
Tap one for the subcontractor
InvoiceWorkStatusAmount
SC-3567
Jon Haskins Plumbing and Heating, 7 May
Plumbing, second fixPaid£525.00
SC-3568
Gary Pullen Electrical, 7 May
Electrics, second fixPaid£175.00
SC-3562
Jon Haskins Plumbing and Heating, 1 May
Plumbing, first fixPaid£525.00
SC-3560
Gary Pullen Electrical, 30 Apr
Electrics, first fixPaid£175.00
Invoices · posted to Xero when sent
Billing →
InvoiceStageStatusNetGrossXero
INV-2296
issued 15 Apr
Deposit
1 line
Paid 21 Apr£2,450.00£2,940.00posted
INV-2313
issued 5 May
Progress
1 line
Paid 21 May£4,900.00£5,880.00posted
INV-2323
issued 15 May
Completion
1 line
Paid 21 May£2,450.00£2,940.00posted
Stages £9,800 + billed extras £0 = £9,800 on invoices. £9,800 sent, £9,800 paid.
HJ
Hannah and James Vickery
Hannah Vickery · client since 1 Mar 2026
Site41 Rowan Drive, Southville
Phone07700 900992
PortalLive: progress, extras, invoices
See what Hannah sees in the portal
Messages in the portal
No messages on this job yet.
People and dates
Project managerKate Lyons
CrewChris Moss, small works
Booked13 Apr 2026
StartedThu 30 Apr
Handed over14 May 2026
Timeline
Handed over and closed
Kate · 14 May 15:00
Jon Haskins Plumbing and Heating: Plumbing, second fix, £525.00
Jon Haskins · 7 May 17:00
Gary Pullen Electrical: Electrics, second fix, £175.00
Gary Pullen · 7 May 17:00
Jon Haskins Plumbing and Heating: Plumbing, first fix, £525.00
Jon Haskins · 1 May 17:00
Gary Pullen Electrical: Electrics, first fix, £175.00
Gary Pullen · 30 Apr 17:00
First day on site: Chris, Sam
Site app · 30 Apr 07:30
Booked: £9,800 ex VAT
Owen · 13 Apr 11:00