LIVE DEMO
Clinic · commercial · fixed price

Job 3946

Complete
Clinic fit-out
For Avonvale Podiatry, Bristol. Crew C with Gareth Price. On site 26 Jan to 3 Feb, handed over 6 Feb 2026.
Agreed price
£30,250
ex VAT
Final margin
18.4%
quoted 21.7%
100% of the work done93 m² floor
Client's portal view
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
Quoted margin21.7%£6,558 on £30,250
Final margin18.4%£5,554 profit
Invoiced so far£30,250of £30,250, £28,737 paid, £1,513 retention held
Where the money went
PersonHoursLabour costDifference
DK
Dave Kerr
Lead fitter, crew C, £35/h at cost
56 h
of 50 h estimated
£1,960
of £1,750
+£210
TA
Tom Ashby
Joiner, crew C, £30/h at cost
56 h
of 50 h estimated
£1,680
of £1,500
+£180
ER
Ellie Rudd
Apprentice joiner, crew C, £16/h at cost
48 h
of 37 h estimated
£768
of £592
+£176
RF
Rob Finch
Decorator, £28/h at cost
16 h
of 15 h estimated
£448
of £420
+£28
SK
Sam Kerridge
Labourer and driver, £22/h at cost
16 h
of 15 h estimated
£352
of £330
+£22
True labour cost. The 3 clinics and practices finished this year really took 1.94 h per m² of floor, against the old rule of 1.8. This job: 93 m² floor, priced on 167 h. Rule of thumb: 1.8 h per m² of floor. New quotes now use the true rate →
Cost week by week
£24,696 spent over 3 weeks, against a £23,692 estimate
LabourMaterialsSubcontract
Extras and variations · 0
Variations →
No extras on this job.
Timesheets · 192 h, £5,208 at cost
Timesheets →
Week ofPersonHoursCostStatus
2 Feb
Tap for the days
DKDave Kerr16 h
2 days
£560.00
at £35/h
approved
from the paper sheets
2 Feb
Tap for the days
EREllie Rudd16 h
2 days
£256.00
at £16/h
approved
from the paper sheets
2 Feb
Tap for the days
RFRob Finch16 h
2 days
£448.00
at £28/h
approved
from the paper sheets
2 Feb
Tap for the days
TATom Ashby16 h
2 days
£480.00
at £30/h
approved
from the paper sheets
26 Jan
Tap for the days
DKDave Kerr40 h
5 days
£1,400.00
at £35/h
approved
from the paper sheets
26 Jan
Tap for the days
EREllie Rudd32 h
4 days
£512.00
at £16/h
approved
from the paper sheets
26 Jan
Tap for the days
SKSam Kerridge16 h
2 days
£352.00
at £22/h
approved
from the paper sheets
26 Jan
Tap for the days
TATom Ashby40 h
5 days
£1,200.00
at £30/h
approved
from the paper sheets
Purchases · 5, £10,638
Purchases →
OrderWhatStatusNet
PO-5152
Cotsmoor Flooring Trade, raised 26 Jan
Safety flooringDelivered 2 Feb, billed£1,913.17
PO-5146
Voltmere Electrical Wholesale, raised 23 Jan
Lighting and electricalDelivered 26 Jan, billed£2,123.55
PO-5145
Kestle Timber, raised 22 Jan
Joinery timber and sheetDelivered 26 Jan, billed£1,735.16
PO-5144
Avonmere Builders Merchants, raised 20 Jan
Partitions, board and ceilingsDelivered 23 Jan, billed£3,164.03
PO-5137
Linmouth Bathroom Supply, raised 17 Jan
Clinical sinks and tapsDelivered 26 Jan, billed£1,702.22
Subcontractor invoices · 5, £8,850
Tap one for the subcontractor
InvoiceWorkStatusAmount
SC-3447
Andy Rees Electrical, 3 Feb
Electrics and data, second fixPaid£1,990.00
SC-3448
Jon Haskins Plumbing and Heating, 3 Feb
Plumbing, second fixPaid£1,550.00
SC-3444
Nick Weller Flooring, 2 Feb
Floor laying, supply-laid by the floor layerPaid£1,770.00
SC-3437
Andy Rees Electrical, 27 Jan
Electrics and data, first fixPaid£1,990.00
SC-3438
Jon Haskins Plumbing and Heating, 27 Jan
Plumbing, first fixPaid£1,550.00
Invoices · posted to Xero when sent
Billing →
InvoiceStageStatusNetGrossXero
INV-2206
issued 16 Dec 2025
Deposit
1 line
Paid 14 Jan£7,562.50£8,621.24
£378 retention held
posted
INV-2234
issued 30 Jan
Progress
1 line
Paid 7 Mar£15,125.00£17,242.50
£756 retention held
posted
INV-2244
issued 9 Feb
Completion
1 line
Paid 9 Mar£7,562.50£8,621.24
£378 retention held
posted
Stages £30,250 + billed extras £0 = £30,250 on invoices. £30,250 sent, £28,737 paid, £1,513 retention held until the defects period ends.
AP
Avonvale Podiatry
Contact: Henry Dando · client since 27 Nov 2025
Site14 North Street, Bristol
Phone0117 496 0409
PortalLive: progress, extras, invoices
See what Henry sees in the portal
Messages in the portal
No messages on this job yet.
People and dates
Project managerGareth Price
CrewCrew C: Dave, Tom, Ellie
Booked14 Dec 2025
StartedMon 26 Jan
Handed over6 Feb 2026
Retention5% held to the end of defects
Timeline
Handed over and closed
Gareth · 6 Feb 15:00
Andy Rees Electrical: Electrics and data, second fix, £1,990.00
Andy Rees · 3 Feb 17:00
Jon Haskins Plumbing and Heating: Plumbing, second fix, £1,550.00
Jon Haskins · 3 Feb 17:00
Nick Weller Flooring: Floor laying, supply-laid by the floor layer, £1,770.00
Nick Weller · 2 Feb 17:00
Andy Rees Electrical: Electrics and data, first fix, £1,990.00
Andy Rees · 27 Jan 17:00
Jon Haskins Plumbing and Heating: Plumbing, first fix, £1,550.00
Jon Haskins · 27 Jan 17:00
First day on site: Dave, Ellie, Sam, Tom
Site app · 26 Jan 07:30
Booked: £30,250 ex VAT
Owen · 14 Dec 2025 11:00