Bathroom · domestic · fixed price

Job 3949

Complete
Family bathroom
For Lisa and Philip Vranch, Keynsham. Crew B with Kate Lyons. On site 23 Jan to 26 Jan, handed over 31 Jan 2026.
Agreed price
£8,550
ex VAT
Final margin
24.3%
quoted 23.9%
100% of the work done12 m² tiled
Client's portal view
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
Quoted margin23.9%£2,045 on £8,550
Final margin24.3%£2,075 profit
Invoiced so far£8,550of £8,550, £8,550 paid
Where the money went
PersonHoursLabour costDifference
MT
Mike Tanner
Lead fitter and tiler, crew B, £34/h at cost
16 h
of 20 h estimated
£544
of £680
-£136
RH
Ryan Hale
Fitter, crew B, £30/h at cost
16 h
of 17.5 h estimated
£480
of £525
-£45
CW
Callum Webb
Apprentice fitter, crew B, £16/h at cost
16 h
of 12.5 h estimated
£256
of £200
+£56
True labour cost. The 25 bathrooms finished this year really took 4.5 h per m² tiled, against the old rule of 4.2. This job: 12 m² tiled, priced on 50 h. Rule of thumb: 4.2 h per m² tiled. New quotes now use the true rate →
Cost week by week
£6,475 spent over 2 weeks, against a £6,505 estimate
LabourMaterialsSubcontract
Extras and variations · 0
Variations →
No extras on this job.
Timesheets · 48 h, £1,280 at cost
Timesheets →
Week ofPersonHoursCostStatus
26 Jan
Tap for the days
CWCallum Webb8 h
1 day
£128.00
at £16/h
approved
from the paper sheets
26 Jan
Tap for the days
MTMike Tanner8 h
1 day
£272.00
at £34/h
approved
from the paper sheets
26 Jan
Tap for the days
RHRyan Hale8 h
1 day
£240.00
at £30/h
approved
from the paper sheets
19 Jan
Tap for the days
CWCallum Webb8 h
1 day
£128.00
at £16/h
approved
from the paper sheets
19 Jan
Tap for the days
MTMike Tanner8 h
1 day
£272.00
at £34/h
approved
from the paper sheets
19 Jan
Tap for the days
RHRyan Hale8 h
1 day
£240.00
at £30/h
approved
from the paper sheets
Purchases · 5, £3,345
Purchases →
OrderWhatStatusNet
PO-5142
Voltmere Electrical Wholesale, raised 20 Jan
Lighting and extractorDelivered 23 Jan, billed£169.15
PO-5143
Avonmere Builders Merchants, raised 20 Jan
Board, tanking and sundriesDelivered 23 Jan, billed£445.52
PO-5139
Kestle Timber, raised 19 Jan
Timber and fixingsDelivered 23 Jan, billed£238.73
PO-5138
Brackwell Tiles, raised 18 Jan
Wall and floor tiles, adhesive, groutDelivered 23 Jan, billed£893.63
PO-5131
Linmouth Bathroom Supply, raised 13 Jan
Sanitaryware and brasswareDelivered 22 Jan, billed£1,597.94
Subcontractor invoices · 5, £1,850
Tap one for the subcontractor
InvoiceWorkStatusAmount
SC-3435
Jon Haskins Plumbing and Heating, 26 Jan
Plumbing, second fixPaid£575.00
SC-3436
Gary Pullen Electrical, 26 Jan
Electrics, second fixPaid£165.00
SC-3430
Jon Haskins Plumbing and Heating, 23 Jan
Plumbing, first fixPaid£575.00
SC-3431
Gary Pullen Electrical, 23 Jan
Electrics, first fixPaid£165.00
SC-3432
Mark Dent Plastering, 23 Jan
Plastering, skim and making goodPaid£370.00
Invoices · posted to Xero when sent
Billing →
InvoiceStageStatusNetGrossXero
INV-2209
issued 24 Dec 2025
Deposit
1 line
Paid 29 Dec 2025£2,137.50£2,565.00posted
INV-2231
issued 26 Jan
Progress
1 line
Paid 1 Feb£4,275.00£5,130.00posted
INV-2238
issued 2 Feb
Completion
1 line
Paid 15 Feb£2,137.50£2,565.00posted
Stages £8,550 + billed extras £0 = £8,550 on invoices. £8,550 sent, £8,550 paid.
LP
Lisa and Philip Vranch
Lisa Vranch · client since 24 Nov 2025
Site34 Belmont Avenue, Keynsham
Phone07700 900835
PortalLive: progress, extras, invoices
See what Lisa sees in the portal
Messages in the portal
No messages on this job yet.
People and dates
Project managerKate Lyons
CrewCrew B: Mike, Ryan, Callum
Booked22 Dec 2025
StartedFri 23 Jan
Handed over31 Jan 2026
Timeline
Handed over and closed
Kate · 31 Jan 15:00
Jon Haskins Plumbing and Heating: Plumbing, second fix, £575.00
Jon Haskins · 26 Jan 17:00
Gary Pullen Electrical: Electrics, second fix, £165.00
Gary Pullen · 26 Jan 17:00
Jon Haskins Plumbing and Heating: Plumbing, first fix, £575.00
Jon Haskins · 23 Jan 17:00
Gary Pullen Electrical: Electrics, first fix, £165.00
Gary Pullen · 23 Jan 17:00
Mark Dent Plastering: Plastering, skim and making good, £370.00
Mark Dent · 23 Jan 17:00
First day on site: Callum, Mike, Ryan
Site app · 23 Jan 07:30
Booked: £8,550 ex VAT
Owen · 22 Dec 2025 11:00