LIVE DEMO
Kitchen · domestic · fixed price

Job 3952

Complete
Kitchen fit-out
For Amanda and James Pocock, Cotham. Crew A with Kate Lyons. On site 18 Feb to 26 Feb, handed over 4 Mar 2026.
Agreed price
£20,300
ex VAT
Final margin
20.7%
quoted 25.7%
100% of the work done13 cabinets
Client's portal view
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
Quoted margin25.7%£5,226 on £20,300
Final margin20.7%£4,208 profit
Invoiced so far£20,300of £20,300, £20,300 paid
Where the money went
PersonHoursLabour costDifference
SR
Steve Rowe
Lead fitter, crew A, £34/h at cost
56 h
of 52.5 h estimated
£1,904
of £1,785
+£119
LD
Liam Doyle
Joiner, crew A, £30/h at cost
56 h
of 52.5 h estimated
£1,680
of £1,575
+£105
JP
Josh Penrose
Apprentice joiner, crew A, £16/h at cost
40 h
of 33 h estimated
£640
of £528
+£112
RF
Rob Finch
Decorator, £28/h at cost
16 h
of 12 h estimated
£448
of £336
+£112
True labour cost. The 15 kitchens finished this year really took 12.95 h per cabinet, against the old rule of 11.5. This job: 13 cabinets, priced on 150 h. Rule of thumb: 11.5 h per cabinet. New quotes now use the true rate →
Cost week by week
£16,092 spent over 2 weeks, against a £15,074 estimate
LabourMaterialsSubcontract
Extras and variations · 0
Variations →
No extras on this job.
Timesheets · 168 h, £4,672 at cost
Timesheets →
Week ofPersonHoursCostStatus
23 Feb
Tap for the days
JPJosh Penrose24 h
3 days
£384.00
at £16/h
approved
from the paper sheets
23 Feb
Tap for the days
LDLiam Doyle32 h
4 days
£960.00
at £30/h
approved
from the paper sheets
23 Feb
Tap for the days
RFRob Finch16 h
2 days
£448.00
at £28/h
approved
from the paper sheets
23 Feb
Tap for the days
SRSteve Rowe32 h
4 days
£1,088.00
at £34/h
approved
from the paper sheets
16 Feb
Tap for the days
JPJosh Penrose16 h
2 days
£256.00
at £16/h
approved
from the paper sheets
16 Feb
Tap for the days
LDLiam Doyle24 h
3 days
£720.00
at £30/h
approved
from the paper sheets
16 Feb
Tap for the days
SRSteve Rowe24 h
3 days
£816.00
at £34/h
approved
from the paper sheets
Purchases · 6, £8,620
Purchases →
OrderWhatStatusNet
PO-5182
Avonmere Builders Merchants, raised 15 Feb
Plaster, board and sundriesDelivered 18 Feb, billed£352.81
PO-5183
Brackwell Tiles, raised 15 Feb
Splashback tiles and adhesiveDelivered 20 Feb, billed£351.64
PO-5184
Voltmere Electrical Wholesale, raised 15 Feb
Lighting and electrical fittingsDelivered 18 Feb, billed£341.95
PO-5178
Kestle Timber, raised 14 Feb
Timber, panels and fixingsDelivered 18 Feb, billed£255.18
PO-5175
Halbrook Worktops, raised 12 Feb
Worktops, templated and fittedDelivered 24 Feb, billed£2,264.77
PO-5150
Wrenfold Kitchen Supply, raised 26 Jan
Kitchen units and doorsDelivered 17 Feb, billed£5,053.19
Subcontractor invoices · 5, £2,800
Tap one for the subcontractor
InvoiceWorkStatusAmount
SC-3475
Gary Pullen Electrical, 26 Feb
Electrics, second fixPaid£630.00
SC-3476
Jon Haskins Plumbing and Heating, 26 Feb
Plumbing, second fixPaid£460.00
SC-3471
Mark Dent Plastering, 20 Feb
Plastering, skim and making goodPaid£620.00
SC-3467
Gary Pullen Electrical, 19 Feb
Electrics, first fixPaid£630.00
SC-3468
Jon Haskins Plumbing and Heating, 19 Feb
Plumbing, first fixPaid£460.00
Invoices · posted to Xero when sent
Billing →
InvoiceStageStatusNetGrossXero
INV-2212
issued 2 Jan
Deposit
1 line
Paid 17 Jan£5,075.00£6,090.00posted
INV-2256
issued 23 Feb
Progress
1 line
Paid 7 Mar£10,150.00£12,180.00posted
INV-2264
issued 5 Mar
Completion
1 line
Paid 21 Mar£5,075.00£6,090.00posted
Stages £20,300 + billed extras £0 = £20,300 on invoices. £20,300 sent, £20,300 paid.
AJ
Amanda and James Pocock
Amanda Pocock · client since 20 Dec 2025
Site54 Church Lane, Cotham
Phone07700 900846
PortalLive: progress, extras, invoices
See what Amanda sees in the portal
Messages in the portal
No messages on this job yet.
People and dates
Project managerKate Lyons
CrewCrew A: Steve, Liam, Josh
Booked30 Dec 2025
StartedWed 18 Feb
Handed over4 Mar 2026
Timeline
Handed over and closed
Kate · 4 Mar 15:00
Gary Pullen Electrical: Electrics, second fix, £630.00
Gary Pullen · 26 Feb 17:00
Jon Haskins Plumbing and Heating: Plumbing, second fix, £460.00
Jon Haskins · 26 Feb 17:00
Mark Dent Plastering: Plastering, skim and making good, £620.00
Mark Dent · 20 Feb 17:00
Gary Pullen Electrical: Electrics, first fix, £630.00
Gary Pullen · 19 Feb 17:00
Jon Haskins Plumbing and Heating: Plumbing, first fix, £460.00
Jon Haskins · 19 Feb 17:00
First day on site: Liam, Steve
Site app · 18 Feb 07:30
Booked: £20,300 ex VAT
Owen · 30 Dec 2025 11:00