LIVE DEMO
Kitchen · domestic · fixed price

Job 3959

Complete
Kitchen fit-out
For Lisa Gazzard, Saltford. Crew A with Kate Lyons. On site 11 Mar to 24 Mar, handed over 29 Mar 2026.
Agreed price
£25,450
ex VAT, +£1,700 extras billed
Final margin
24.5%
quoted 24.5%
100% of the work done17 cabinets
Client's portal view
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
Extras captured on site
1 extra on this job
Every extra ↓
Quoted margin24.5%£6,244 on £25,450
Final margin24.5%£6,649 profit
Invoiced so far£27,150of £27,150, £27,150 paid
Where the money went
PersonHoursLabour costDifference
SR
Steve Rowe
Lead fitter, crew A, £34/h at cost
72 h
of 68.5 h estimated
£2,448
of £2,329
+£119
LD
Liam Doyle
Joiner, crew A, £30/h at cost
72 h
of 68.5 h estimated
£2,160
of £2,055
+£105
JP
Josh Penrose
Apprentice joiner, crew A, £16/h at cost
56 h
of 43 h estimated
£896
of £688
+£208
RF
Rob Finch
Decorator, £28/h at cost
16 h
of 15.5 h estimated
£448
of £434
+£14
True labour cost. The 15 kitchens finished this year really took 12.95 h per cabinet, against the old rule of 11.5. This job: 17 cabinets, priced on 195.5 h. Rule of thumb: 11.5 h per cabinet. New quotes now use the true rate →
Cost week by week
£20,501 spent over 3 weeks, against a £19,206 estimate
LabourMaterialsSubcontract
Extras and variations · 1
Variations →
Timesheets · 216 h, £5,952 at cost
Timesheets →
Week ofPersonHoursCostStatus
23 Mar
Tap for the days
JPJosh Penrose8 h
1 day
£128.00
at £16/h
approved
from the paper sheets
23 Mar
Tap for the days
LDLiam Doyle8 h
1 day
£240.00
at £30/h
approved
from the paper sheets
23 Mar
Tap for the days
RFRob Finch16 h
2 days
£448.00
at £28/h
approved
from the paper sheets
23 Mar
Tap for the days
SRSteve Rowe8 h
1 day
£272.00
at £34/h
approved
from the paper sheets
16 Mar
Tap for the days
JPJosh Penrose32 h
4 days
£512.00
at £16/h
approved
from the paper sheets
16 Mar
Tap for the days
LDLiam Doyle40 h
5 days
£1,200.00
at £30/h
approved
from the paper sheets
16 Mar
Tap for the days
SRSteve Rowe40 h
5 days
£1,360.00
at £34/h
approved
from the paper sheets
9 Mar
Tap for the days
JPJosh Penrose16 h
2 days
£256.00
at £16/h
approved
from the paper sheets
9 Mar
Tap for the days
LDLiam Doyle24 h
3 days
£720.00
at £30/h
approved
from the paper sheets
9 Mar
Tap for the days
SRSteve Rowe24 h
3 days
£816.00
at £34/h
approved
from the paper sheets
Purchases · 6, £11,399
Purchases →
OrderWhatStatusNet
PO-5217
Brackwell Tiles, raised 12 Mar
Splashback tiles and adhesiveDelivered 17 Mar, billed£469.27
PO-5214
Voltmere Electrical Wholesale, raised 9 Mar
Lighting and electrical fittingsDelivered 12 Mar, billed£464.97
PO-5215
Avonmere Builders Merchants, raised 9 Mar
Plaster, board and sundriesDelivered 12 Mar, billed£463.55
PO-5210
Kestle Timber, raised 8 Mar
Timber, panels and fixingsDelivered 12 Mar, billed£345.84
PO-5212
Halbrook Worktops, raised 8 Mar
Worktops, templated and fittedDelivered 20 Mar, billed£3,128.62
PO-5187
Wrenfold Kitchen Supply, raised 16 Feb
Kitchen units and doorsDelivered 10 Mar, billed£6,526.44
Subcontractor invoices · 5, £3,150
Tap one for the subcontractor
InvoiceWorkStatusAmount
SC-3510
Gary Pullen Electrical, 24 Mar
Electrics, second fixPaid£710.00
SC-3511
Jon Haskins Plumbing and Heating, 24 Mar
Plumbing, second fixPaid£520.00
SC-3503
Mark Dent Plastering, 17 Mar
Plastering, skim and making goodPaid£690.00
SC-3499
Jon Haskins Plumbing and Heating, 13 Mar
Plumbing, first fixPaid£520.00
SC-3498
Gary Pullen Electrical, 12 Mar
Electrics, first fixPaid£710.00
Invoices · posted to Xero when sent
Billing →
InvoiceStageStatusNetGrossXero
INV-2229
issued 22 Jan
Deposit
1 line
Paid 4 Feb£6,362.50£7,635.00posted
INV-2276
issued 17 Mar
Progress
1 line
Paid 2 Apr£12,725.00£15,270.00posted
INV-2284
issued 30 Mar
Completion
2 lines, with V-3959-1
Paid 10 Apr£8,062.50£9,675.00posted
Stages £25,450 + billed extras £1,700 = £27,150 on invoices. £27,150 sent, £27,150 paid.
LG
Lisa Gazzard
Lisa Gazzard · client since 10 Jan 2026
Site9 Linden Close, Saltford
Phone07700 900654
PortalLive: progress, extras, invoices
See what Lisa sees in the portal
Messages in the portal
No messages on this job yet.
People and dates
Project managerKate Lyons
CrewCrew A: Steve, Liam, Josh
Booked20 Jan 2026
StartedWed 11 Mar
Handed over29 Mar 2026
Timeline
Handed over and closed
Kate · 29 Mar 15:00
Gary Pullen Electrical: Electrics, second fix, £710.00
Gary Pullen · 24 Mar 17:00
Jon Haskins Plumbing and Heating: Plumbing, second fix, £520.00
Jon Haskins · 24 Mar 17:00
Mark Dent Plastering: Plastering, skim and making good, £690.00
Mark Dent · 17 Mar 17:00
Jon Haskins Plumbing and Heating: Plumbing, first fix, £520.00
Jon Haskins · 13 Mar 17:00
Gary Pullen Electrical: Electrics, first fix, £710.00
Gary Pullen · 12 Mar 17:00
First day on site: Liam, Steve
Site app · 11 Mar 07:30
Booked: £25,450 ex VAT
Owen · 20 Jan 11:00