LIVE DEMO
Café · commercial · fixed price

Job 3973

Complete
Café refit: counter and seating
For Fennel and Fig Deli, Bristol. Crew C with Gareth Price. On site 20 Apr to 29 Apr, handed over 7 May 2026.
Agreed price
£30,300
ex VAT
Final margin
18.6%
quoted 19.3%
100% of the work done76 m² floor
Client's portal view
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
Quoted margin19.3%£5,837 on £30,300
Final margin18.6%£5,650 profit
Invoiced so far£30,300of £30,300, £28,785 paid, £1,515 retention held
Where the money went
PersonHoursLabour costDifference
DK
Dave Kerr
Lead fitter, crew C, £35/h at cost
64 h
of 59.5 h estimated
£2,240
of £2,083
+£158
TA
Tom Ashby
Joiner, crew C, £30/h at cost
64 h
of 59.5 h estimated
£1,920
of £1,785
+£135
ER
Ellie Rudd
Apprentice joiner, crew C, £16/h at cost
48 h
of 43.5 h estimated
£768
of £696
+£72
RF
Rob Finch
Decorator, £28/h at cost
16 h
of 18 h estimated
£448
of £504
-£56
SK
Sam Kerridge
Labourer and driver, £22/h at cost
16 h
of 18 h estimated
£352
of £396
-£44
True labour cost. The 3 cafés finished this year really took 2.81 h per m² of floor, against the old rule of 2.6. This job: 76 m² floor, priced on 198.5 h. Rule of thumb: 2.6 h per m² of floor. New quotes now use the true rate →
Cost week by week
£24,650 spent over 2 weeks, against a £24,464 estimate
LabourMaterialsSubcontract
Extras and variations · 0
Variations →
No extras on this job.
Timesheets · 208 h, £5,728 at cost
Timesheets →
Week ofPersonHoursCostStatus
27 Apr
Tap for the days
DKDave Kerr24 h
3 days
£840.00
at £35/h
approved
from the paper sheets
27 Apr
Tap for the days
EREllie Rudd16 h
2 days
£256.00
at £16/h
approved
from the paper sheets
27 Apr
Tap for the days
RFRob Finch16 h
2 days
£448.00
at £28/h
approved
from the paper sheets
27 Apr
Tap for the days
TATom Ashby24 h
3 days
£720.00
at £30/h
approved
from the paper sheets
20 Apr
Tap for the days
DKDave Kerr40 h
5 days
£1,400.00
at £35/h
approved
from the paper sheets
20 Apr
Tap for the days
EREllie Rudd32 h
4 days
£512.00
at £16/h
approved
from the paper sheets
20 Apr
Tap for the days
SKSam Kerridge16 h
2 days
£352.00
at £22/h
approved
from the paper sheets
20 Apr
Tap for the days
TATom Ashby40 h
5 days
£1,200.00
at £30/h
approved
from the paper sheets
Purchases · 6, £10,572
Purchases →
OrderWhatStatusNet
PO-5272
Cotsmoor Flooring Trade, raised 21 Apr
FlooringDelivered 28 Apr, billed£1,645.09
PO-5268
Brackwell Tiles, raised 18 Apr
Wall tiles and adhesiveDelivered 23 Apr, billed£1,379.56
PO-5266
Avonmere Builders Merchants, raised 17 Apr
Partitions, board and sundriesDelivered 20 Apr, billed£2,302.66
PO-5267
Voltmere Electrical Wholesale, raised 17 Apr
Lighting and electricalDelivered 20 Apr, billed£1,776.52
PO-5265
Kestle Timber, raised 16 Apr
Joinery timber and sheetDelivered 20 Apr, billed£1,793.70
PO-5263
Halbrook Worktops, raised 15 Apr
Counter worktops, templated and fittedDelivered 27 Apr, billed£1,674.88
Subcontractor invoices · 6, £8,350
Tap one for the subcontractor
InvoiceWorkStatusAmount
SC-3555
Andy Rees Electrical, 29 Apr
Electrics, second fixPaid£1,670.00
SC-3556
Jon Haskins Plumbing and Heating, 29 Apr
Plumbing, second fixPaid£1,255.00
SC-3554
Nick Weller Flooring, 28 Apr
Floor laying, supply-laid by the floor layerPaid£1,250.00
SC-3553
Lee Carver Tiling, 24 Apr
Tiling, tilingPaid£1,250.00
SC-3546
Andy Rees Electrical, 21 Apr
Electrics, first fixPaid£1,670.00
SC-3547
Jon Haskins Plumbing and Heating, 21 Apr
Plumbing, first fixPaid£1,255.00
Invoices · posted to Xero when sent
Billing →
InvoiceStageStatusNetGrossXero
INV-2273
issued 12 Mar
Deposit
1 line
Paid 6 Apr£7,575.00£8,635.50
£379 retention held
posted
INV-2307
issued 24 Apr
Progress
1 line
Paid 17 May£15,150.00£17,271.00
£758 retention held
posted
INV-2317
issued 8 May
Completion
1 line
Paid 12 Jun£7,575.00£8,635.50
£379 retention held
posted
Stages £30,300 + billed extras £0 = £30,300 on invoices. £30,300 sent, £28,785 paid, £1,515 retention held until the defects period ends.
FF
Fennel and Fig Deli
Contact: Claire Thatcher · client since 19 Feb 2026
Site92 Corn Street, Bristol
Phone0117 496 0519
PortalLive: progress, extras, invoices
See what Claire sees in the portal
Messages in the portal
No messages on this job yet.
People and dates
Project managerGareth Price
CrewCrew C: Dave, Tom, Ellie
Booked10 Mar 2026
StartedMon 20 Apr
Handed over7 May 2026
Retention5% held to the end of defects
Timeline
Handed over and closed
Gareth · 7 May 15:00
Andy Rees Electrical: Electrics, second fix, £1,670.00
Andy Rees · 29 Apr 17:00
Jon Haskins Plumbing and Heating: Plumbing, second fix, £1,255.00
Jon Haskins · 29 Apr 17:00
Nick Weller Flooring: Floor laying, supply-laid by the floor layer, £1,250.00
Nick Weller · 28 Apr 17:00
Lee Carver Tiling: Tiling, tiling, £1,250.00
Lee Carver · 24 Apr 17:00
Andy Rees Electrical: Electrics, first fix, £1,670.00
Andy Rees · 21 Apr 17:00
Jon Haskins Plumbing and Heating: Plumbing, first fix, £1,255.00
Jon Haskins · 21 Apr 17:00
First day on site: Dave, Ellie, Sam, Tom
Site app · 20 Apr 07:30
Booked: £30,300 ex VAT
Owen · 10 Mar 11:00