Bathroom · domestic · fixed price

Job 3985

Complete
Downstairs cloakroom
For Graham Bracey, Thornbury. Chris Moss (small works) with Kate Lyons. On site 19 May to 21 May, handed over 30 May 2026.
Agreed price
£8,750
ex VAT, +£380 extras billed
Final margin
29.0%
quoted 29.1%
100% of the work done5 m²
Client's portal view
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
Extras captured on site
1 extra on this job
Every extra ↓
Quoted margin29.1%£2,548 on £8,750
Final margin29.0%£2,649 profit
Invoiced so far£9,130of £9,130, £9,130 paid
Where the money went
PersonHoursLabour costDifference
CM
Chris Moss
Small works and snagging fitter, £30/h at cost
24 h
of 24 h estimated
£720
of £720
on budget
SK
Sam Kerridge
Labourer and driver, £22/h at cost
8 h
of 6 h estimated
£176
of £132
+£44
Rule of thumb: 6 h per m².
Cost week by week
£6,481 spent over 1 week, against a £6,202 estimate
LabourMaterialsSubcontract
Extras and variations · 1
Variations →
Timesheets · 32 h, £896 at cost
Timesheets →
Week ofPersonHoursCostStatus
18 May
Tap for the days
CMChris Moss24 h
3 days
£720.00
at £30/h
approved
from the paper sheets
18 May
Tap for the days
SKSam Kerridge8 h
1 day
£176.00
at £22/h
approved
from the paper sheets
Purchases · 4, £4,017
Purchases →
OrderWhatStatusNet
PO-5305
Avonmere Builders Merchants, raised 16 May
Board and sundriesDelivered 19 May, billed£398.64
PO-5304
Brackwell Tiles, raised 15 May
Tiles and adhesiveDelivered 20 May, billed£617.43
PO-5292
Linmouth Bathroom Supply, raised 9 May
Sanitaryware and brasswareDelivered 18 May, billed£1,997.65
PO-5287
Wrenfold Kitchen Supply, raised 4 May
Utility unitsDelivered 19 May, billed£1,003.61
Subcontractor invoices · 4, £1,568
Tap one for the subcontractor
InvoiceWorkStatusAmount
SC-3585
Jon Haskins Plumbing and Heating, 21 May
Plumbing, second fixPaid£588.00
SC-3586
Gary Pullen Electrical, 21 May
Electrics, second fixPaid£196.00
SC-3583
Jon Haskins Plumbing and Heating, 19 May
Plumbing, first fixPaid£588.00
SC-3584
Gary Pullen Electrical, 19 May
Electrics, first fixPaid£196.00
Invoices · posted to Xero when sent
Billing →
InvoiceStageStatusNetGrossXero
INV-2315
issued 5 May
Deposit
1 line
Paid 21 May£2,187.50£2,625.00posted
INV-2328
issued 20 May
Progress
1 line
Paid 26 May£4,375.00£5,250.00posted
INV-2337
issued 1 Jun
Completion
2 lines, with V-3985-1
Paid 16 Jun£2,567.50£3,081.00posted
Stages £8,750 + billed extras £380 = £9,130 on invoices. £9,130 sent, £9,130 paid.
GB
Graham Bracey
Graham Bracey · client since 20 Mar 2026
Site72 Victoria Walk, Thornbury
Phone07700 900949
PortalLive: progress, extras, invoices
See what Graham sees in the portal
Messages in the portal
No messages on this job yet.
People and dates
Project managerKate Lyons
CrewChris Moss, small works
Booked3 May 2026
StartedTue 19 May
Handed over30 May 2026
Timeline
Handed over and closed
Kate · 30 May 15:00
Jon Haskins Plumbing and Heating: Plumbing, second fix, £588.00
Jon Haskins · 21 May 17:00
Gary Pullen Electrical: Electrics, second fix, £196.00
Gary Pullen · 21 May 17:00
Jon Haskins Plumbing and Heating: Plumbing, first fix, £588.00
Jon Haskins · 19 May 17:00
Gary Pullen Electrical: Electrics, first fix, £196.00
Gary Pullen · 19 May 17:00
First day on site: Chris, Sam
Site app · 19 May 07:30
Booked: £8,750 ex VAT
Owen · 3 May 11:00