Bathroom · domestic · fixed price

Job 3990

Complete
Downstairs cloakroom
For Louise and Ian Holloway, Knowle. Chris Moss (small works) with Kate Lyons. On site 4 Jun to 8 Jun, handed over 11 Jun 2026.
Agreed price
£8,750
ex VAT, +£350 extras billed
Final margin
30.3%
quoted 29.1%
100% of the work done5 m²
Client's portal view
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
Extras captured on site
1 extra on this job
Every extra ↓
Quoted margin29.1%£2,548 on £8,750
Final margin30.3%£2,760 profit
Invoiced so far£9,100of £9,100, £9,100 paid
Where the money went
PersonHoursLabour costDifference
CM
Chris Moss
Small works and snagging fitter, £30/h at cost
24 h
of 24 h estimated
£720
of £720
on budget
SK
Sam Kerridge
Labourer and driver, £22/h at cost
8 h
of 6 h estimated
£176
of £132
+£44
Rule of thumb: 6 h per m².
Cost week by week
£6,340 spent over 2 weeks, against a £6,202 estimate
LabourMaterialsSubcontract
Extras and variations · 1
Variations →
Timesheets · 32 h, £896 at cost
Timesheets →
Week ofPersonHoursCostStatus
8 Jun
Tap for the days
CMChris Moss8 h
1 day
£240.00
at £30/h
approved
1 Jun
Tap for the days
CMChris Moss16 h
2 days
£480.00
at £30/h
approved
1 Jun
Tap for the days
SKSam Kerridge8 h
1 day
£176.00
at £22/h
approved
Purchases · 4, £3,932
Purchases →
OrderWhatStatusNet
PO-5324
Avonmere Builders Merchants, raised 1 Jun
Board and sundriesDelivered 4 Jun, billed£393.79
PO-5323
Brackwell Tiles, raised 31 May
Tiles and adhesiveDelivered 5 Jun, billed£578.59
PO-5314
Linmouth Bathroom Supply, raised 25 May
Sanitaryware and brasswareDelivered 3 Jun, billed£1,943.24
PO-5302
Wrenfold Kitchen Supply, raised 14 May
Utility unitsDelivered 4 Jun, billed£1,016.37
Subcontractor invoices · 4, £1,512
Tap one for the subcontractor
InvoiceWorkStatusAmount
SC-3605
Jon Haskins Plumbing and Heating, 8 Jun
Plumbing, second fixPaid£567.00
SC-3606
Gary Pullen Electrical, 8 Jun
Electrics, second fixPaid£189.00
SC-3601
Jon Haskins Plumbing and Heating, 4 Jun
Plumbing, first fixPaid£567.00
SC-3602
Gary Pullen Electrical, 4 Jun
Electrics, first fixPaid£189.00
Invoices · posted to Xero when sent
Billing →
InvoiceStageStatusNetGrossXero
INV-2324
issued 15 May
Deposit
1 line
Paid 23 May£2,187.50£2,625.00posted
INV-2344
issued 8 Jun
Progress
1 line
Paid 20 Jun£4,375.00£5,250.00posted
INV-2349
issued 12 Jun
Completion
2 lines, with V-3990-1
Paid 25 Jun£2,537.50£3,045.00posted
Stages £8,750 + billed extras £350 = £9,100 on invoices. £9,100 sent, £9,100 paid.
LI
Louise and Ian Holloway
Louise Holloway · client since 5 Apr 2026
Site57 Hawthorn Way, Knowle
Phone07700 900916
PortalLive: progress, extras, invoices
See what Louise sees in the portal
Messages in the portal
No messages on this job yet.
People and dates
Project managerKate Lyons
CrewChris Moss, small works
Booked13 May 2026
StartedThu 4 Jun
Handed over11 Jun 2026
Timeline
Handed over and closed
Kate · 11 Jun 15:00
Jon Haskins Plumbing and Heating: Plumbing, second fix, £567.00
Jon Haskins · 8 Jun 17:00
Gary Pullen Electrical: Electrics, second fix, £189.00
Gary Pullen · 8 Jun 17:00
Jon Haskins Plumbing and Heating: Plumbing, first fix, £567.00
Jon Haskins · 4 Jun 17:00
Gary Pullen Electrical: Electrics, first fix, £189.00
Gary Pullen · 4 Jun 17:00
First day on site: Chris, Sam
Site app · 4 Jun 07:30
Booked: £8,750 ex VAT
Owen · 13 May 11:00