Bathroom · domestic · fixed price

Job 4008

Snagging
Family bathroom
For Claire Hobbs, Bishopston. Crew B with Kate Lyons. Started 10 Aug, handover Fri 23 Oct.
Agreed price
£12,450
ex VAT
Margin now
22.0%
quoted 23.6%
100% of the work done25 m² tiled
Client's portal view
Job note
Shower screen chipped on delivery. The replacement lands Thu 22 Oct; Chris fits it Fri 23 Oct.
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
Live from the site app
Quoted margin23.6%£2,938 on £12,450
Margin now22.0%£2,745 profit on the forecast
Invoiced so far£9,338of £12,450, £9,338 paid
Where the money went
PersonHoursLabour costDifference
MT
Mike Tanner
Lead fitter and tiler, crew B, £34/h at cost
40 h
of 42 h estimated
£1,360
of £1,428
-£68
RH
Ryan Hale
Fitter, crew B, £30/h at cost
40 h
of 37 h estimated
£1,200
of £1,110
+£90
CW
Callum Webb
Apprentice fitter, crew B, £16/h at cost
32 h
of 26.5 h estimated
£512
of £424
+£88
True labour cost. The 25 bathrooms finished this year really took 4.5 h per m² tiled, against the old rule of 4.2. This job: 25 m² tiled, priced on 105.5 h. Rule of thumb: 4.2 h per m² tiled. New quotes now use the true rate →
Cost week by week
£9,705 spent over 2 weeks, against a £9,512 estimate
LabourMaterialsSubcontract
Extras and variations · 0
Variations →
No extras on this job.
Timesheets · 112 h, £3,072 at cost
Timesheets →
Week ofPersonHoursCostStatus
10 Aug
Tap for the days
CWCallum Webb32 h
4 days
£512.00
at £16/h
approved
10 Aug
Tap for the days
MTMike Tanner40 h
5 days
£1,360.00
at £34/h
approved
10 Aug
Tap for the days
RHRyan Hale40 h
5 days
£1,200.00
at £30/h
approved
Purchases · 5, £4,383
Purchases →
OrderWhatStatusNet
PO-5427
Voltmere Electrical Wholesale, raised 7 Aug
Lighting and extractorDelivered 10 Aug, billed£227.29
PO-5428
Brackwell Tiles, raised 7 Aug
Wall and floor tiles, adhesive, groutDelivered 12 Aug, billed£1,153.75
PO-5429
Avonmere Builders Merchants, raised 7 Aug
Board, tanking and sundriesDelivered 10 Aug, billed£571.37
PO-5426
Kestle Timber, raised 6 Aug
Timber and fixingsDelivered 10 Aug, billed£305.42
PO-5416
Linmouth Bathroom Supply, raised 29 Jul
Sanitaryware and brasswareDelivered 7 Aug, billed£2,125.04
Subcontractor invoices · 5, £2,250
Tap one for the subcontractor
InvoiceWorkStatusAmount
SC-3703
Jon Haskins Plumbing and Heating, 14 Aug
Plumbing, second fixPaid£700.00
SC-3704
Gary Pullen Electrical, 14 Aug
Electrics, second fixPaid£205.00
SC-3701
Mark Dent Plastering, 12 Aug
Plastering, skim and making goodPaid£440.00
SC-3699
Jon Haskins Plumbing and Heating, 11 Aug
Plumbing, first fixPaid£700.00
SC-3697
Gary Pullen Electrical, 10 Aug
Electrics, first fixPaid£205.00
Invoices · posted to Xero when sent
Billing →
InvoiceStageStatusNetGrossXero
INV-2381
issued 15 Jul
Deposit
1 line
Paid 28 Jul£3,112.50£3,735.00posted
INV-2405
issued 12 Aug
Progress
1 line
Paid 25 Aug£6,225.00£7,470.00posted
DRAFT-07
goes out 23 Oct
Completion
1 line
Draft, goes out 23 Oct£3,112.50£3,735.00not yet
Stages £12,450 + billed extras £0 = £12,450 on invoices. £9,338 sent, £9,338 paid.
CH
Claire Hobbs
Claire Hobbs · client since 6 Jul 2026
Site56 Kingsley Road, Bishopston
Phone07700 900572
PortalLive: progress, extras, invoices
See what Claire sees in the portal
Messages in the portal
No messages on this job yet.
People and dates
Project managerKate Lyons
CrewCrew B: Mike, Ryan, Callum
Booked13 Jul 2026
StartedMon 10 Aug
HandoverFri 23 Oct
On the schedule
Schedule →
This week and next
Timeline
Jon Haskins Plumbing and Heating: Plumbing, second fix, £700.00
Jon Haskins · 14 Aug 17:00
Gary Pullen Electrical: Electrics, second fix, £205.00
Gary Pullen · 14 Aug 17:00
Mark Dent Plastering: Plastering, skim and making good, £440.00
Mark Dent · 12 Aug 17:00
Jon Haskins Plumbing and Heating: Plumbing, first fix, £700.00
Jon Haskins · 11 Aug 17:00
Gary Pullen Electrical: Electrics, first fix, £205.00
Gary Pullen · 10 Aug 17:00
First day on site: Callum, Mike, Ryan
Site app · 10 Aug 07:30
Booked: £12,450 ex VAT
Owen · 13 Jul 11:00