Kitchen · domestic · fixed price

Job 4009

Complete
Kitchen worktop replacement
For Lisa and Colin Ogden, Saltford. Chris Moss (small works) with Kate Lyons. On site 3 Aug to 7 Aug, handed over 16 Aug 2026.
Agreed price
£11,000
ex VAT, +£380 extras billed
Final margin
30.3%
quoted 31.4%
100% of the work done11 cabinets
Client's portal view
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
Extras captured on site
1 extra on this job
Every extra ↓
Quoted margin31.4%£3,452 on £11,000
Final margin30.3%£3,445 profit
Invoiced so far£11,380of £11,380, £11,380 paid
Where the money went
PersonHoursLabour costDifference
CM
Chris Moss
Small works and snagging fitter, £30/h at cost
40 h
of 35 h estimated
£1,200
of £1,050
+£150
SK
Sam Kerridge
Labourer and driver, £22/h at cost
8 h
of 9 h estimated
£176
of £198
-£22
Rule of thumb: 4 h per cabinet.
Cost week by week
£7,935 spent over 1 week, against a £7,548 estimate
LabourMaterialsSubcontract
Extras and variations · 1
Variations →
Timesheets · 48 h, £1,376 at cost
Timesheets →
Week ofPersonHoursCostStatus
3 Aug
Tap for the days
CMChris Moss40 h
5 days
£1,200.00
at £30/h
approved
3 Aug
Tap for the days
SKSam Kerridge8 h
1 day
£176.00
at £22/h
approved
Purchases · 3, £5,914
Purchases →
OrderWhatStatusNet
PO-5422
Avonmere Builders Merchants, raised 31 Jul
SundriesDelivered 3 Aug, billed£289.03
PO-5414
Halbrook Worktops, raised 25 Jul
Worktops, templated and fittedDelivered 6 Aug, billed£3,187.04
PO-5396
Wrenfold Kitchen Supply, raised 16 Jul
Replacement doors and panelsDelivered 3 Aug, billed£2,438.06
Subcontractor invoices · 2, £645
Tap one for the subcontractor
InvoiceWorkStatusAmount
SC-3696
Jon Haskins Plumbing and Heating, 7 Aug
Plumbing, second fixPaid£322.50
SC-3692
Jon Haskins Plumbing and Heating, 4 Aug
Plumbing, first fixPaid£322.50
Invoices · posted to Xero when sent
Billing →
InvoiceStageStatusNetGrossXero
INV-2382
issued 17 Jul
Deposit
1 line
Paid 30 Jul£2,750.00£3,300.00posted
INV-2401
issued 5 Aug
Progress
1 line
Paid 16 Aug£5,500.00£6,600.00posted
INV-2409
issued 17 Aug
Completion
2 lines, with V-4009-1
Paid 28 Aug£3,130.00£3,756.00posted
Stages £11,000 + billed extras £380 = £11,380 on invoices. £11,380 sent, £11,380 paid.
LC
Lisa and Colin Ogden
Lisa Ogden · client since 4 Jun 2026
Site9 Victoria Walk, Saltford
Phone07700 900676
PortalLive: progress, extras, invoices
See what Lisa sees in the portal
Messages in the portal
No messages on this job yet.
People and dates
Project managerKate Lyons
CrewChris Moss, small works
Booked15 Jul 2026
StartedMon 3 Aug
Handed over16 Aug 2026
Timeline
Handed over and closed
Kate · 16 Aug 15:00
Jon Haskins Plumbing and Heating: Plumbing, second fix, £322.50
Jon Haskins · 7 Aug 17:00
Jon Haskins Plumbing and Heating: Plumbing, first fix, £322.50
Jon Haskins · 4 Aug 17:00
First day on site: Chris
Site app · 3 Aug 07:30
Booked: £11,000 ex VAT
Owen · 15 Jul 11:00