Bathroom · domestic · fixed price

Job 4023

Snagging
Downstairs cloakroom
For Karen Lyle, Winterbourne. Chris Moss (small works) with Kate Lyons. Started 21 Sep, handover Thu 22 Oct.
Agreed price
£10,500
ex VAT
Margin now
30.5%
quoted 31.8%
100% of the work done8 m²
Client's portal view
Job note
Basin tap dripping; a replacement is fitted on Thu 22 Oct, then the completion invoice goes.
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
Live from the site app
Quoted margin31.8%£3,336 on £10,500
Margin now30.5%£3,199 profit on the forecast
Invoiced so far£7,875of £10,500, £7,875 paid
Where the money went
PersonHoursLabour costDifference
CM
Chris Moss
Small works and snagging fitter, £30/h at cost
40 h
of 38.5 h estimated
£1,200
of £1,155
+£45
SK
Sam Kerridge
Labourer and driver, £22/h at cost
8 h
of 9.5 h estimated
£176
of £209
-£33
Rule of thumb: 6 h per m².
Cost week by week
£7,301 spent over 2 weeks, against a £7,164 estimate
LabourMaterialsSubcontract
Extras and variations · 0
Variations →
No extras on this job.
Timesheets · 48 h, £1,376 at cost
Timesheets →
Week ofPersonHoursCostStatus
21 Sep
Tap for the days
CMChris Moss40 h
5 days
£1,200.00
at £30/h
approved
21 Sep
Tap for the days
SKSam Kerridge8 h
1 day
£176.00
at £22/h
approved
Purchases · 4, £4,525
Purchases →
OrderWhatStatusNet
PO-5482
Brackwell Tiles, raised 18 Sep
Tiles and adhesiveDelivered 23 Sep, billed£684.15
PO-5483
Avonmere Builders Merchants, raised 18 Sep
Board and sundriesDelivered 21 Sep, billed£435.74
PO-5474
Linmouth Bathroom Supply, raised 9 Sep
Sanitaryware and brasswareDelivered 18 Sep, billed£2,280.23
PO-5471
Wrenfold Kitchen Supply, raised 8 Sep
Utility unitsDelivered 21 Sep, billed£1,125.30
Subcontractor invoices · 4, £1,400
Tap one for the subcontractor
InvoiceWorkStatusAmount
SC-3748
Jon Haskins Plumbing and Heating, 25 Sep
Plumbing, second fixApproved, in Xero£525.00
SC-3749
Gary Pullen Electrical, 25 Sep
Electrics, second fixApproved, in Xero£175.00
SC-3746
Jon Haskins Plumbing and Heating, 22 Sep
Plumbing, first fixApproved, in Xero£525.00
SC-3745
Gary Pullen Electrical, 21 Sep
Electrics, first fixApproved, in Xero£175.00
Invoices · posted to Xero when sent
Billing →
InvoiceStageStatusNetGrossXero
INV-2427
issued 9 Sep
Deposit
1 line
Paid 14 Sep£2,625.00£3,150.00posted
INV-2435
issued 23 Sep
Progress
1 line
Paid 29 Sep£5,250.00£6,300.00posted
DRAFT-06
goes out 22 Oct
Completion
1 line
Draft, goes out 22 Oct£2,625.00£3,150.00not yet
Stages £10,500 + billed extras £0 = £10,500 on invoices. £7,875 sent, £7,875 paid.
KL
Karen Lyle
Karen Lyle · client since 24 Aug 2026
Site11 Station Road, Winterbourne
Phone07700 900435
PortalLive: progress, extras, invoices
See what Karen sees in the portal
Messages in the portal
No messages on this job yet.
People and dates
Project managerKate Lyons
CrewChris Moss, small works
Booked7 Sep 2026
StartedMon 21 Sep
HandoverThu 22 Oct
On the schedule
Schedule →
This week and next
Timeline
Jon Haskins Plumbing and Heating: Plumbing, second fix, £525.00
Jon Haskins · 25 Sep 17:00
Gary Pullen Electrical: Electrics, second fix, £175.00
Gary Pullen · 25 Sep 17:00
Jon Haskins Plumbing and Heating: Plumbing, first fix, £525.00
Jon Haskins · 22 Sep 17:00
Gary Pullen Electrical: Electrics, first fix, £175.00
Gary Pullen · 21 Sep 17:00
First day on site: Chris, Sam
Site app · 21 Sep 07:30
Booked: £10,500 ex VAT
Owen · 7 Sep 11:00