LIVE DEMO
Kitchen · domestic · fixed price

Job 4028

In progress
Worktops and doors replacement
For Philip and Jenny Webber, Knowle. Chris Moss (small works) with Kate Lyons. Started 5 Oct, handover Wed 21 Oct.
Agreed price
£10,050
ex VAT
Margin now
30.6%
quoted 31.0%
80% of the work done10 cabinets
Client's portal view
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
Live from the site app
Quoted margin31.0%£3,114 on £10,050
Margin now30.6%£3,073 profit on the forecast
Invoiced so far£7,538of £10,050, £2,513 paid
Where the money went
PersonHoursLabour costLeft in the estimate
CM
Chris Moss
Small works and snagging fitter, £30/h at cost
32 h
of 32 h estimated
£960
of £960
£0
SK
Sam Kerridge
Labourer and driver, £22/h at cost
0 h
of 8 h estimated
£0
of £176
£176
Rule of thumb: 4 h per cabinet.
Cost week by week
£3,597 spent over 2 weeks, against a £6,936 estimate
LabourMaterialsSubcontract
Extras and variations · 0
Variations →
No extras on this job.
Timesheets · 32 h, £960 at cost
Timesheets →
Week ofPersonHoursCostStatus
12 Oct
Tap for the days
CMChris Moss16 h
2 days
£480.00
at £30/h
submitted, approve Fri
5 Oct
Tap for the days
CMChris Moss16 h
2 days
£480.00
at £30/h
approved
Purchases · 3, £5,190
Purchases →
OrderWhatStatusNet
PO-5511
Halbrook Worktops, raised 4 Oct
Worktops, templated and fittedOn order, due 16 Oct£2,853.29
PO-5507
Avonmere Builders Merchants, raised 3 Oct
SundriesDelivered 6 Oct, bill to come£266.59
PO-5488
Wrenfold Kitchen Supply, raised 22 Sep
Replacement doors and panelsDelivered 6 Oct, bill to come£2,070.32
Subcontractor invoices · 1, £300
Tap one for the subcontractor
InvoiceWorkStatusAmount
SC-3760
Jon Haskins Plumbing and Heating, 7 Oct
Plumbing, first fixApproved, in Xero£300.00
Invoices · posted to Xero when sent
Billing →
InvoiceStageStatusNetGrossXero
INV-2436
issued 23 Sep
Deposit
1 line
Paid 4 Oct£2,512.50£3,015.00posted
INV-2454
issued 14 Oct
Progress
1 line
Sent, due 28 Oct£5,025.00£6,030.00posted
Stages £7,538 + billed extras £0 = £7,538 on invoices. £7,538 sent, £2,513 paid.
PJ
Philip and Jenny Webber
Jenny Webber · client since 15 Sep 2026
Site33 Park Avenue, Knowle
Phone07700 900285
PortalLive: progress, extras, invoices
See what Jenny sees in the portal
Messages in the portal
No messages on this job yet.
People and dates
Project managerKate Lyons
CrewChris Moss, small works
Booked21 Sep 2026
StartedMon 5 Oct
HandoverWed 21 Oct
On the schedule
Schedule →
This week and next
Timeline
Jon Haskins Plumbing and Heating: Plumbing, first fix, £300.00
Jon Haskins · 7 Oct 17:00
First day on site: Chris
Site app · 5 Oct 07:30
Booked: £10,050 ex VAT
Owen · 21 Sep 11:00