Clinic · commercial · fixed price
Job 3941
CompleteTreatment rooms fit-out
For Brookmead Hearing, Bristol. Crew C with Gareth Price. On site 5 Jan to 21 Jan, handed over 30 Jan 2026.
Agreed price
£47,500
ex VAT
Final margin
17.2%
quoted 20.7%
100% of the work done148 m² floor
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
CostEstimateActual so farFinalDifference
Labour296 h logged against 266.5 h estimated, at each person's true cost rate£7,336£8,072£8,072+£73610.0% overMaterials5 purchases received£16,300£17,229£17,229+£9295.7% overSubcontract5 invoices from the electrician, plumber and floor layer£14,050£14,050£14,050On budgetTotal cost£37,686£39,351£39,351+£1,6654.4% overQuoted margin20.7%£9,814 on £47,500
Final margin17.2%£8,149 profit
Invoiced so far£47,500of £47,500, £45,125 paid, £2,375 retention held
Where the money went
| Person | Hours | Labour cost | Difference |
|---|---|---|---|
DK Dave Kerr Lead fitter, crew C, £35/h at cost | 88 h of 80 h estimated | £3,080 of £2,800 | +£280 |
TA Tom Ashby Joiner, crew C, £30/h at cost | 88 h of 80 h estimated | £2,640 of £2,400 | +£240 |
ER Ellie Rudd Apprentice joiner, crew C, £16/h at cost | 72 h of 58.5 h estimated | £1,152 of £936 | +£216 |
RF Rob Finch Decorator, £28/h at cost | 24 h of 24 h estimated | £672 of £672 | on budget |
SK Sam Kerridge Labourer and driver, £22/h at cost | 24 h of 24 h estimated | £528 of £528 | on budget |
True labour cost. The 3 clinics and practices finished this year really took 1.94 h per m² of floor, against the old rule of 1.8. This job: 148 m² floor, priced on 266.5 h. Rule of thumb: 1.8 h per m² of floor. New quotes now use the true rate →
| Estimate line | Estimate | Ordered | Received | Difference |
|---|---|---|---|---|
Partitions, board and ceilings Avonmere Builders Merchants, PO-5108 | £4,890 | £5,257 | £5,257 | +£367 |
Joinery timber and sheet Kestle Timber, PO-5117 | £2,610 | £2,690 | £2,690 | +£80 |
Lighting and electrical Voltmere Electrical Wholesale, PO-5119 | £3,260 | £3,406 | £3,406 | +£146 |
Safety flooring Cotsmoor Flooring Trade, PO-5128 | £2,930 | £3,079 | £3,079 | +£149 |
Clinical sinks and taps Linmouth Bathroom Supply, PO-5107 | £2,610 | £2,799 | £2,799 | +£189 |
Materials count when they are delivered and signed for on site. Nothing is on order and not received. Supplier bills post to Xero from here.
| Trade | Agreed | Invoiced | Difference |
|---|---|---|---|
Electrics and data Andy Rees Electrical, 2 invoices | £6,320 | £6,320 | on the agreed price |
Plumbing Jon Haskins Plumbing and Heating, 2 invoices | £4,920 | £4,920 | on the agreed price |
Floor laying Nick Weller Flooring, 1 invoice | £2,810 | £2,810 | on the agreed price |
The forecast counts each trade at its agreed price until it invoices more.
Agreed price
5% retention held on each invoice, stage invoices at 25%, 50% and 25%
£47,500.00
Revenue
£47,500.00
Labour
final
- £8,072.00
Materials
final
- £17,229.18
Subcontract
final
- £14,050.00
Profit
17.2% margin, quoted at 20.7% (£9,814)
£8,148.82
Cost week by week
£39,351 spent over 4 weeks, against a £37,686 estimate
LabourMaterialsSubcontract
| Week of | Hours | Labour | Materials | Subcontract | Total |
|---|---|---|---|---|---|
| 29 Dec 2025 | 0 h | £0 | £5,257 | £0 | £5,257 |
| 5 Jan | 136 h | £3,640 | £8,894 | £5,620 | £18,154 |
| 12 Jan | 112 h | £3,112 | £0 | £0 | £3,112 |
| 19 Jan | 48 h | £1,320 | £3,079 | £8,430 | £12,829 |
Extras and variations · 0
Variations →No extras on this job.
Timesheets · 296 h, £8,072 at cost
Timesheets →| Week of | Person | Hours | Cost | Status |
|---|---|---|---|---|
| 19 Jan Tap for the days Mon 19 Jan8 hTS-00087 | DKDave Kerr | 8 h 1 day | £280.00 at £35/h | approved from the paper sheets |
| 19 Jan Tap for the days Mon 19 Jan8 hTS-00088 | EREllie Rudd | 8 h 1 day | £128.00 at £16/h | approved from the paper sheets |
| 19 Jan Tap for the days Mon 19 Jan8 hTS-00092 Tue 20 Jan8 hTS-00099 Wed 21 Jan8 hTS-00103 | RFRob Finch | 24 h 3 days | £672.00 at £28/h | approved from the paper sheets |
| 19 Jan Tap for the days Mon 19 Jan8 hTS-00095 | TATom Ashby | 8 h 1 day | £240.00 at £30/h | approved from the paper sheets |
| 12 Jan Tap for the days Mon 12 Jan8 hTS-00050 Tue 13 Jan8 hTS-00056 Wed 14 Jan8 hTS-00062 Thu 15 Jan8 hTS-00068 Fri 16 Jan8 hTS-00079 | DKDave Kerr | 40 h 5 days | £1,400.00 at £35/h | approved from the paper sheets |
| 12 Jan Tap for the days Mon 12 Jan8 hTS-00051 Tue 13 Jan8 hTS-00057 Thu 15 Jan8 hTS-00069 Fri 16 Jan8 hTS-00080 | EREllie Rudd | 32 h 4 days | £512.00 at £16/h | approved from the paper sheets |
| 12 Jan Tap for the days Mon 12 Jan8 hTS-00055 Tue 13 Jan8 hTS-00061 Wed 14 Jan8 hTS-00066 Thu 15 Jan8 hTS-00076 Fri 16 Jan8 hTS-00084 | TATom Ashby | 40 h 5 days | £1,200.00 at £30/h | approved from the paper sheets |
| 5 Jan Tap for the days Mon 5 Jan8 hTS-00003 Tue 6 Jan8 hTS-00014 Wed 7 Jan8 hTS-00024 Thu 8 Jan8 hTS-00032 Fri 9 Jan8 hTS-00042 | DKDave Kerr | 40 h 5 days | £1,400.00 at £35/h | approved from the paper sheets |
| 5 Jan Tap for the days Mon 5 Jan8 hTS-00004 Tue 6 Jan8 hTS-00015 Thu 8 Jan8 hTS-00033 Fri 9 Jan8 hTS-00043 | EREllie Rudd | 32 h 4 days | £512.00 at £16/h | approved from the paper sheets |
| 5 Jan Tap for the days Mon 5 Jan8 hTS-00009 Tue 6 Jan8 hTS-00020 Wed 7 Jan8 hTS-00028 | SKSam Kerridge | 24 h 3 days | £528.00 at £22/h | approved from the paper sheets |
| 5 Jan Tap for the days Mon 5 Jan8 hTS-00011 Tue 6 Jan8 hTS-00022 Wed 7 Jan8 hTS-00030 Thu 8 Jan8 hTS-00040 Fri 9 Jan8 hTS-00049 | TATom Ashby | 40 h 5 days | £1,200.00 at £30/h | approved from the paper sheets |
Purchases · 5, £17,229
Purchases →| Order | What | Status | Net |
|---|---|---|---|
| PO-5128 Cotsmoor Flooring Trade, raised 12 Jan | Safety flooring | Delivered 19 Jan, billed | £3,078.56 |
| PO-5119 Voltmere Electrical Wholesale, raised 3 Jan | Lighting and electrical | Delivered 6 Jan, billed | £3,405.52 |
| PO-5117 Kestle Timber, raised 2 Jan | Joinery timber and sheet | Delivered 6 Jan, billed | £2,689.54 |
| PO-5108 Avonmere Builders Merchants, raised 30 Dec 2025 | Partitions, board and ceilings | Delivered 2 Jan, billed | £5,256.67 |
| PO-5107 Linmouth Bathroom Supply, raised 28 Dec 2025 | Clinical sinks and taps | Delivered 6 Jan, billed | £2,798.89 |
Subcontractor invoices · 5, £14,050
Tap one for the subcontractor| Invoice | Work | Status | Amount |
|---|---|---|---|
| SC-3425 Andy Rees Electrical, 21 Jan | Electrics and data, second fix | Paid | £3,160.00 |
Andy Rees ElectricalElectrician, Nailsea. Day rate £280. Insured to Jan 2027. Commercial jobs, data and emergency lighting. | |||
| SC-3426 Jon Haskins Plumbing and Heating, 21 Jan | Plumbing, second fix | Paid | £2,460.00 |
Jon Haskins Plumbing and HeatingPlumber, Bedminster. Day rate £250. Insured to May 2027. Gas Safe registered. | |||
| SC-3423 Nick Weller Flooring, 20 Jan | Floor laying, supply-laid by the floor layer | Paid | £2,810.00 |
Nick Weller FlooringFloor layer, Yate. Day rate £240. Insured to Aug 2027. Commercial vinyl and safety flooring. | |||
| SC-3407 Jon Haskins Plumbing and Heating, 7 Jan | Plumbing, first fix | Paid | £2,460.00 |
Jon Haskins Plumbing and HeatingPlumber, Bedminster. Day rate £250. Insured to May 2027. Gas Safe registered. | |||
| SC-3403 Andy Rees Electrical, 6 Jan | Electrics and data, first fix | Paid | £3,160.00 |
Andy Rees ElectricalElectrician, Nailsea. Day rate £280. Insured to Jan 2027. Commercial jobs, data and emergency lighting. | |||
Invoices · posted to Xero when sent
Billing →| Invoice | Stage | Status | Net | Gross | Xero |
|---|---|---|---|---|---|
| INV-2201 issued 25 Nov 2025 | Deposit 1 line | Paid 28 Dec 2025 | £11,875.00 | £13,537.50 £594 retention held | posted |
| INV-2219 issued 13 Jan | Progress 1 line | Paid 6 Feb | £23,750.00 | £27,075.00 £1,188 retention held | posted |
| INV-2236 issued 2 Feb | Completion 1 line | Paid 24 Feb | £11,875.00 | £13,537.50 £594 retention held | posted |
Stages £47,500 + billed extras £0 = £47,500 on invoices. £47,500 sent, £45,125 paid, £2,375 retention held until the defects period ends.
Client
Client page →Brookmead Hearing
Contact: Lucy Nott · client since 6 Nov 2025
Site76 Regent Street, Bristol
Phone0117 496 0742
PortalLive: progress, extras, invoices
Messages in the portal
No messages on this job yet.
People and dates
Project managerGareth Price
CrewCrew C: Dave, Tom, Ellie
Booked23 Nov 2025
StartedMon 5 Jan
Handed over30 Jan 2026
Retention5% held to the end of defects
Timeline
Handed over and closed
Gareth · 30 Jan 15:00
Andy Rees Electrical: Electrics and data, second fix, £3,160.00
Andy Rees · 21 Jan 17:00
Jon Haskins Plumbing and Heating: Plumbing, second fix, £2,460.00
Jon Haskins · 21 Jan 17:00
Nick Weller Flooring: Floor laying, supply-laid by the floor layer, £2,810.00
Nick Weller · 20 Jan 17:00
Delivered: Safety flooring from Cotsmoor Flooring Trade (PO-5128, £3,078.56)
Dave Kerr · 19 Jan 08:15
Jon Haskins Plumbing and Heating: Plumbing, first fix, £2,460.00
Jon Haskins · 7 Jan 17:00
Andy Rees Electrical: Electrics and data, first fix, £3,160.00
Andy Rees · 6 Jan 17:00
Delivered: Clinical sinks and taps from Linmouth Bathroom Supply (PO-5107, £2,798.89)
Dave Kerr · 6 Jan 08:15
Delivered: Joinery timber and sheet from Kestle Timber (PO-5117, £2,689.54)
Dave Kerr · 6 Jan 08:15
Delivered: Lighting and electrical from Voltmere Electrical Wholesale (PO-5119, £3,405.52)
Dave Kerr · 6 Jan 08:15
First day on site: Dave, Ellie, Sam, Tom
Site app · 5 Jan 07:30
Deposit invoice INV-2201 sent and posted to Xero, £11,875.00 ex VAT; paid 28 Dec 2025
Auto · 25 Nov 2025 16:00
Booked: £47,500 ex VAT
Owen · 23 Nov 2025 11:00