Kitchen · domestic · fixed price
Job 3945
CompleteKitchen-diner fit-out
For Lisa Kingscott, Downend. Crew A with Kate Lyons. On site 30 Jan to 11 Feb, handed over 19 Feb 2026.
Agreed price
£24,650
ex VAT
Final margin
22.7%
quoted 26.4%
100% of the work done16 cabinets
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
CostEstimateActual so farFinalDifference
Labour216 h logged against 184 h estimated, at each person's true cost rate£5,182£5,952£5,952+£77014.9% overMaterials6 purchases received£9,900£10,057£10,057+£1571.6% overSubcontract5 invoices from the electrician, plumber and plasterer£3,050£3,050£3,050On budgetTotal cost£18,132£19,059£19,059+£9275.1% overQuoted margin26.4%£6,518 on £24,650
Final margin22.7%£5,591 profit
Invoiced so far£24,650of £24,650, £24,650 paid
Where the money went
| Person | Hours | Labour cost | Difference |
|---|---|---|---|
SR Steve Rowe Lead fitter, crew A, £34/h at cost | 72 h of 64.5 h estimated | £2,448 of £2,193 | +£255 |
LD Liam Doyle Joiner, crew A, £30/h at cost | 72 h of 64.5 h estimated | £2,160 of £1,935 | +£225 |
JP Josh Penrose Apprentice joiner, crew A, £16/h at cost | 56 h of 40.5 h estimated | £896 of £648 | +£248 |
RF Rob Finch Decorator, £28/h at cost | 16 h of 14.5 h estimated | £448 of £406 | +£42 |
True labour cost. The 15 kitchens finished this year really took 12.95 h per cabinet, against the old rule of 11.5. This job: 16 cabinets, priced on 184 h. Rule of thumb: 11.5 h per cabinet. New quotes now use the true rate →
| Estimate line | Estimate | Ordered | Received | Difference |
|---|---|---|---|---|
Kitchen units and doors Wrenfold Kitchen Supply, PO-5123 | £5,740 | £5,832 | £5,832 | +£92 |
Worktops, templated and fitted Halbrook Worktops, PO-5158 | £2,670 | £2,726 | £2,726 | +£56 |
Plaster, board and sundries Avonmere Builders Merchants, PO-5155 | £400 | £401 | £401 | +£1 |
Timber, panels and fixings Kestle Timber, PO-5151 | £300 | £300 | £300 | on budget |
Lighting and electrical fittings Voltmere Electrical Wholesale, PO-5156 | £400 | £405 | £405 | +£5 |
Splashback tiles and adhesive Brackwell Tiles, PO-5159 | £390 | £393 | £393 | +£3 |
Materials count when they are delivered and signed for on site. Nothing is on order and not received. Supplier bills post to Xero from here.
| Trade | Agreed | Invoiced | Difference |
|---|---|---|---|
Electrics Gary Pullen Electrical, 2 invoices | £1,370 | £1,370 | on the agreed price |
Plumbing Jon Haskins Plumbing and Heating, 2 invoices | £1,010 | £1,010 | on the agreed price |
Plastering Mark Dent Plastering, 1 invoice | £670 | £670 | on the agreed price |
The forecast counts each trade at its agreed price until it invoices more.
Agreed price
stage invoices at 25%, 50% and 25%
£24,650.00
Revenue
£24,650.00
Labour
final
- £5,952.00
Materials
final
- £10,056.68
Subcontract
final
- £3,050.00
Profit
22.7% margin, quoted at 26.4% (£6,518)
£5,591.32
Cost week by week
£19,059 spent over 3 weeks, against a £18,132 estimate
LabourMaterialsSubcontract
| Week of | Hours | Labour | Materials | Subcontract | Total |
|---|---|---|---|---|---|
| 26 Jan | 24 h | £640 | £6,938 | £0 | £7,578 |
| 2 Feb | 112 h | £3,072 | £393 | £1,860 | £5,325 |
| 9 Feb | 80 h | £2,240 | £2,726 | £1,190 | £6,156 |
Extras and variations · 0
Variations →No extras on this job.
Timesheets · 216 h, £5,952 at cost
Timesheets →| Week of | Person | Hours | Cost | Status |
|---|---|---|---|---|
| 9 Feb Tap for the days Mon 9 Feb8 hTS-00179 Tue 10 Feb8 hTS-00187 | JPJosh Penrose | 16 h 2 days | £256.00 at £16/h | approved from the paper sheets |
| 9 Feb Tap for the days Mon 9 Feb8 hTS-00180 Tue 10 Feb8 hTS-00188 Wed 11 Feb8 hTS-00196 | LDLiam Doyle | 24 h 3 days | £720.00 at £30/h | approved from the paper sheets |
| 9 Feb Tap for the days Tue 10 Feb8 hTS-00190 Wed 11 Feb8 hTS-00198 | RFRob Finch | 16 h 2 days | £448.00 at £28/h | approved from the paper sheets |
| 9 Feb Tap for the days Mon 9 Feb8 hTS-00183 Tue 10 Feb8 hTS-00193 Wed 11 Feb8 hTS-00201 | SRSteve Rowe | 24 h 3 days | £816.00 at £34/h | approved from the paper sheets |
| 2 Feb Tap for the days Mon 2 Feb8 hTS-00150 Tue 3 Feb8 hTS-00160 Thu 5 Feb8 hTS-00170 Fri 6 Feb8 hTS-00174 | JPJosh Penrose | 32 h 4 days | £512.00 at £16/h | approved from the paper sheets |
| 2 Feb Tap for the days Mon 2 Feb8 hTS-00151 Tue 3 Feb8 hTS-00161 Wed 4 Feb8 hTS-00167 Thu 5 Feb8 hTS-00171 Fri 6 Feb8 hTS-00175 | LDLiam Doyle | 40 h 5 days | £1,200.00 at £30/h | approved from the paper sheets |
| 2 Feb Tap for the days Mon 2 Feb8 hTS-00155 Tue 3 Feb8 hTS-00164 Wed 4 Feb8 hTS-00168 Thu 5 Feb8 hTS-00172 Fri 6 Feb8 hTS-00176 | SRSteve Rowe | 40 h 5 days | £1,360.00 at £34/h | approved from the paper sheets |
| 26 Jan Tap for the days Fri 30 Jan8 hTS-00141 | JPJosh Penrose | 8 h 1 day | £128.00 at £16/h | approved from the paper sheets |
| 26 Jan Tap for the days Fri 30 Jan8 hTS-00142 | LDLiam Doyle | 8 h 1 day | £240.00 at £30/h | approved from the paper sheets |
| 26 Jan Tap for the days Fri 30 Jan8 hTS-00145 | SRSteve Rowe | 8 h 1 day | £272.00 at £34/h | approved from the paper sheets |
Purchases · 6, £10,057
Purchases →| Order | What | Status | Net |
|---|---|---|---|
| PO-5159 Brackwell Tiles, raised 30 Jan | Splashback tiles and adhesive | Delivered 4 Feb, billed | £392.66 |
| PO-5158 Halbrook Worktops, raised 28 Jan | Worktops, templated and fitted | Delivered 9 Feb, billed | £2,725.96 |
| PO-5155 Avonmere Builders Merchants, raised 27 Jan | Plaster, board and sundries | Delivered 30 Jan, billed | £400.85 |
| PO-5156 Voltmere Electrical Wholesale, raised 27 Jan | Lighting and electrical fittings | Delivered 30 Jan, billed | £404.88 |
| PO-5151 Kestle Timber, raised 26 Jan | Timber, panels and fixings | Delivered 30 Jan, billed | £300.43 |
| PO-5123 Wrenfold Kitchen Supply, raised 7 Jan | Kitchen units and doors | Delivered 29 Jan, billed | £5,831.90 |
Subcontractor invoices · 5, £3,050
Tap one for the subcontractor| Invoice | Work | Status | Amount |
|---|---|---|---|
| SC-3457 Gary Pullen Electrical, 11 Feb | Electrics, second fix | Paid | £685.00 |
Gary Pullen ElectricalElectrician, Kingswood. Day rate £260. Insured to Mar 2027. Domestic jobs. Part P registered. | |||
| SC-3458 Jon Haskins Plumbing and Heating, 11 Feb | Plumbing, second fix | Paid | £505.00 |
Jon Haskins Plumbing and HeatingPlumber, Bedminster. Day rate £250. Insured to May 2027. Gas Safe registered. | |||
| SC-3450 Mark Dent Plastering, 4 Feb | Plastering, skim and making good | Paid | £670.00 |
Mark Dent PlasteringPlasterer, Brislington. Day rate £220. Insured to Feb 2027. Skim and dry-lining. | |||
| SC-3442 Gary Pullen Electrical, 2 Feb | Electrics, first fix | Paid | £685.00 |
Gary Pullen ElectricalElectrician, Kingswood. Day rate £260. Insured to Mar 2027. Domestic jobs. Part P registered. | |||
| SC-3443 Jon Haskins Plumbing and Heating, 2 Feb | Plumbing, first fix | Paid | £505.00 |
Jon Haskins Plumbing and HeatingPlumber, Bedminster. Day rate £250. Insured to May 2027. Gas Safe registered. | |||
Invoices · posted to Xero when sent
Billing →| Invoice | Stage | Status | Net | Gross | Xero |
|---|---|---|---|---|---|
| INV-2205 issued 15 Dec 2025 | Deposit 1 line | Paid 25 Dec 2025 | £6,162.50 | £7,395.00 | posted |
| INV-2241 issued 5 Feb | Progress 1 line | Paid 18 Feb | £12,325.00 | £14,790.00 | posted |
| INV-2254 issued 20 Feb | Completion 1 line | Paid 4 Mar | £6,162.50 | £7,395.00 | posted |
Stages £24,650 + billed extras £0 = £24,650 on invoices. £24,650 sent, £24,650 paid.
Client
Client page →Lisa Kingscott
Lisa Kingscott · client since 1 Dec 2025
Site21 Hollybush Lane, Downend
Phone07700 900123
PortalLive: progress, extras, invoices
Messages in the portal
No messages on this job yet.
People and dates
Project managerKate Lyons
CrewCrew A: Steve, Liam, Josh
Booked11 Dec 2025
StartedFri 30 Jan
Handed over19 Feb 2026
Timeline
Handed over and closed
Kate · 19 Feb 15:00
Gary Pullen Electrical: Electrics, second fix, £685.00
Gary Pullen · 11 Feb 17:00
Jon Haskins Plumbing and Heating: Plumbing, second fix, £505.00
Jon Haskins · 11 Feb 17:00
Delivered: Worktops, templated and fitted from Halbrook Worktops (PO-5158, £2,725.96)
Steve Rowe · 9 Feb 08:15
Mark Dent Plastering: Plastering, skim and making good, £670.00
Mark Dent · 4 Feb 17:00
Delivered: Splashback tiles and adhesive from Brackwell Tiles (PO-5159, £392.66)
Steve Rowe · 4 Feb 08:15
Gary Pullen Electrical: Electrics, first fix, £685.00
Gary Pullen · 2 Feb 17:00
Jon Haskins Plumbing and Heating: Plumbing, first fix, £505.00
Jon Haskins · 2 Feb 17:00
Delivered: Timber, panels and fixings from Kestle Timber (PO-5151, £300.43)
Steve Rowe · 30 Jan 08:15
Delivered: Plaster, board and sundries from Avonmere Builders Merchants (PO-5155, £400.85)
Steve Rowe · 30 Jan 08:15
Delivered: Lighting and electrical fittings from Voltmere Electrical Wholesale (PO-5156, £404.88)
Steve Rowe · 30 Jan 08:15
First day on site: Josh, Liam, Steve
Site app · 30 Jan 07:30
Delivered: Kitchen units and doors from Wrenfold Kitchen Supply (PO-5123, £5,831.90)
Steve Rowe · 29 Jan 08:15
Deposit invoice INV-2205 sent and posted to Xero, £6,162.50 ex VAT; paid 25 Dec 2025
Auto · 15 Dec 2025 16:00
Booked: £24,650 ex VAT
Owen · 11 Dec 2025 11:00