Café · commercial · fixed price
Job 3953
CompleteCafé fit-out
For Copperwick Coffee, Bristol. Crew C with Gareth Price. On site 10 Feb to 27 Feb, handed over 9 Mar 2026.
Agreed price
£39,300
ex VAT
Final margin
17.0%
quoted 22.3%
100% of the work done95 m² floor
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
CostEstimateActual so farFinalDifference
Labour272 h logged against 246.5 h estimated, at each person's true cost rate£6,782£7,424£7,424+£6429.5% overMaterials6 purchases received£13,300£13,903£13,903+£6034.5% overSubcontract6 invoices from the electrician, plumber, floor layer and tiler£10,450£11,296£11,296+£8468.1% overTotal cost£30,532£32,623£32,623+£2,0916.8% overQuoted margin22.3%£8,768 on £39,300
Final margin17.0%£6,677 profit
Invoiced so far£39,300of £39,300, £37,335 paid, £1,965 retention held
Where the money went
| Person | Hours | Labour cost | Difference |
|---|---|---|---|
DK Dave Kerr Lead fitter, crew C, £35/h at cost | 80 h of 74 h estimated | £2,800 of £2,590 | +£210 |
TA Tom Ashby Joiner, crew C, £30/h at cost | 80 h of 74 h estimated | £2,400 of £2,220 | +£180 |
ER Ellie Rudd Apprentice joiner, crew C, £16/h at cost | 64 h of 54.5 h estimated | £1,024 of £872 | +£152 |
RF Rob Finch Decorator, £28/h at cost | 24 h of 22 h estimated | £672 of £616 | +£56 |
SK Sam Kerridge Labourer and driver, £22/h at cost | 24 h of 22 h estimated | £528 of £484 | +£44 |
True labour cost. The 3 cafés finished this year really took 2.81 h per m² of floor, against the old rule of 2.6. This job: 95 m² floor, priced on 246.5 h. Rule of thumb: 2.6 h per m² of floor. New quotes now use the true rate →
| Estimate line | Estimate | Ordered | Received | Difference |
|---|---|---|---|---|
Counter worktops, templated and fitted Halbrook Worktops, PO-5173 | £2,130 | £2,257 | £2,257 | +£127 |
Partitions, board and sundries Avonmere Builders Merchants, PO-5170 | £2,930 | £3,058 | £3,058 | +£128 |
Joinery timber and sheet Kestle Timber, PO-5168 | £2,260 | £2,318 | £2,318 | +£58 |
Lighting and electrical Voltmere Electrical Wholesale, PO-5171 | £2,260 | £2,395 | £2,395 | +£135 |
Flooring Cotsmoor Flooring Trade, PO-5188 | £2,000 | £2,094 | £2,094 | +£94 |
Wall tiles and adhesive Brackwell Tiles, PO-5174 | £1,720 | £1,780 | £1,780 | +£60 |
Materials count when they are delivered and signed for on site. Nothing is on order and not received. Supplier bills post to Xero from here.
| Trade | Agreed | Invoiced | Difference |
|---|---|---|---|
Electrics Andy Rees Electrical, 2 invoices | £4,180 | £4,519 | +£339 |
Plumbing Jon Haskins Plumbing and Heating, 2 invoices | £3,140 | £3,394 | +£254 |
Floor laying Nick Weller Flooring, 1 invoice | £1,570 | £1,697 | +£127 |
Tiling Lee Carver Tiling, 1 invoice | £1,560 | £1,686 | +£126 |
The forecast counts each trade at its agreed price until it invoices more.
Agreed price
5% retention held on each invoice, stage invoices at 25%, 50% and 25%
£39,300.00
Revenue
£39,300.00
Labour
final
- £7,424.00
Materials
final
- £13,902.78
Subcontract
final
- £11,296.45
Profit
17.0% margin, quoted at 22.3% (£8,768)
£6,676.77
Cost week by week
£32,623 spent over 3 weeks, against a £30,532 estimate
LabourMaterialsSubcontract
| Week of | Hours | Labour | Materials | Subcontract | Total |
|---|---|---|---|---|---|
| 9 Feb | 112 h | £2,992 | £7,772 | £3,956 | £14,720 |
| 16 Feb | 112 h | £3,112 | £1,780 | £1,686 | £6,579 |
| 23 Feb | 48 h | £1,320 | £4,351 | £5,654 | £11,325 |
Extras and variations · 0
Variations →No extras on this job.
Timesheets · 272 h, £7,424 at cost
Timesheets →| Week of | Person | Hours | Cost | Status |
|---|---|---|---|---|
| 23 Feb Tap for the days Mon 23 Feb8 hTS-00245 | DKDave Kerr | 8 h 1 day | £280.00 at £35/h | approved from the paper sheets |
| 23 Feb Tap for the days Mon 23 Feb8 hTS-00246 | EREllie Rudd | 8 h 1 day | £128.00 at £16/h | approved from the paper sheets |
| 23 Feb Tap for the days Mon 23 Feb8 hTS-00249 Tue 24 Feb8 hTS-00254 Fri 27 Feb8 hTS-00270 | RFRob Finch | 24 h 3 days | £672.00 at £28/h | approved from the paper sheets |
| 23 Feb Tap for the days Mon 23 Feb8 hTS-00251 | TATom Ashby | 8 h 1 day | £240.00 at £30/h | approved from the paper sheets |
| 16 Feb Tap for the days Mon 16 Feb8 hTS-00210 Tue 17 Feb8 hTS-00214 Wed 18 Feb8 hTS-00220 Thu 19 Feb8 hTS-00229 Fri 20 Feb8 hTS-00238 | DKDave Kerr | 40 h 5 days | £1,400.00 at £35/h | approved from the paper sheets |
| 16 Feb Tap for the days Mon 16 Feb8 hTS-00211 Tue 17 Feb8 hTS-00215 Thu 19 Feb8 hTS-00230 Fri 20 Feb8 hTS-00239 | EREllie Rudd | 32 h 4 days | £512.00 at £16/h | approved from the paper sheets |
| 16 Feb Tap for the days Mon 16 Feb8 hTS-00212 Tue 17 Feb8 hTS-00218 Wed 18 Feb8 hTS-00226 Thu 19 Feb8 hTS-00236 Fri 20 Feb8 hTS-00243 | TATom Ashby | 40 h 5 days | £1,200.00 at £30/h | approved from the paper sheets |
| 9 Feb Tap for the days Tue 10 Feb8 hTS-00185 Wed 11 Feb8 hTS-00195 Thu 12 Feb8 hTS-00203 Fri 13 Feb8 hTS-00207 | DKDave Kerr | 32 h 4 days | £1,120.00 at £35/h | approved from the paper sheets |
| 9 Feb Tap for the days Tue 10 Feb8 hTS-00186 Thu 12 Feb8 hTS-00204 Fri 13 Feb8 hTS-00208 | EREllie Rudd | 24 h 3 days | £384.00 at £16/h | approved from the paper sheets |
| 9 Feb Tap for the days Tue 10 Feb8 hTS-00192 Wed 11 Feb8 hTS-00200 Thu 12 Feb8 hTS-00205 | SKSam Kerridge | 24 h 3 days | £528.00 at £22/h | approved from the paper sheets |
| 9 Feb Tap for the days Tue 10 Feb8 hTS-00194 Wed 11 Feb8 hTS-00202 Thu 12 Feb8 hTS-00206 Fri 13 Feb8 hTS-00209 | TATom Ashby | 32 h 4 days | £960.00 at £30/h | approved from the paper sheets |
Purchases · 6, £13,903
Purchases →| Order | What | Status | Net |
|---|---|---|---|
| PO-5188 Cotsmoor Flooring Trade, raised 18 Feb | Flooring | Delivered 25 Feb, billed | £2,093.97 |
| PO-5174 Brackwell Tiles, raised 12 Feb | Wall tiles and adhesive | Delivered 17 Feb, billed | £1,780.24 |
| PO-5173 Halbrook Worktops, raised 11 Feb | Counter worktops, templated and fitted | Delivered 23 Feb, billed | £2,257.06 |
| PO-5170 Avonmere Builders Merchants, raised 8 Feb | Partitions, board and sundries | Delivered 11 Feb, billed | £3,058.44 |
| PO-5171 Voltmere Electrical Wholesale, raised 8 Feb | Lighting and electrical | Delivered 11 Feb, billed | £2,395.08 |
| PO-5168 Kestle Timber, raised 7 Feb | Joinery timber and sheet | Delivered 11 Feb, billed | £2,317.99 |
Subcontractor invoices · 6, £11,296
Tap one for the subcontractor| Invoice | Work | Status | Amount |
|---|---|---|---|
| SC-3479 Andy Rees Electrical, 27 Feb | Electrics, second fix | Paid | £2,259.29 |
Andy Rees ElectricalElectrician, Nailsea. Day rate £280. Insured to Jan 2027. Commercial jobs, data and emergency lighting. | |||
| SC-3480 Jon Haskins Plumbing and Heating, 27 Feb | Plumbing, second fix | Paid | £1,697.17 |
Jon Haskins Plumbing and HeatingPlumber, Bedminster. Day rate £250. Insured to May 2027. Gas Safe registered. | |||
| SC-3474 Nick Weller Flooring, 25 Feb | Floor laying, supply-laid by the floor layer | Paid | £1,697.17 |
Nick Weller FlooringFloor layer, Yate. Day rate £240. Insured to Aug 2027. Commercial vinyl and safety flooring. | |||
| SC-3472 Lee Carver Tiling, 20 Feb | Tiling, tiling | Paid | £1,686.36 |
Lee Carver TilingTiler, Portishead. Day rate £230. Insured to Apr 2027. Large-format and commercial tiling. | |||
| SC-3461 Andy Rees Electrical, 12 Feb | Electrics, first fix | Paid | £2,259.29 |
Andy Rees ElectricalElectrician, Nailsea. Day rate £280. Insured to Jan 2027. Commercial jobs, data and emergency lighting. | |||
| SC-3462 Jon Haskins Plumbing and Heating, 12 Feb | Plumbing, first fix | Paid | £1,697.17 |
Jon Haskins Plumbing and HeatingPlumber, Bedminster. Day rate £250. Insured to May 2027. Gas Safe registered. | |||
Invoices · posted to Xero when sent
Billing →| Invoice | Stage | Status | Net | Gross | Xero |
|---|---|---|---|---|---|
| INV-2213 issued 5 Jan | Deposit 1 line | Paid 10 Feb | £9,825.00 | £11,200.50 £491 retention held | posted |
| INV-2251 issued 18 Feb | Progress 1 line | Paid 8 Mar | £19,650.00 | £22,401.00 £983 retention held | posted |
| INV-2270 issued 10 Mar | Completion 1 line | Paid 29 Mar | £9,825.00 | £11,200.50 £491 retention held | posted |
Stages £39,300 + billed extras £0 = £39,300 on invoices. £39,300 sent, £37,335 paid, £1,965 retention held until the defects period ends.
Client
Client page →Copperwick Coffee
Contact: Anna Rossiter · client since 12 Dec 2025
Site13 North Street, Bristol
Phone0117 496 0524
PortalLive: progress, extras, invoices
Messages in the portal
No messages on this job yet.
People and dates
Project managerGareth Price
CrewCrew C: Dave, Tom, Ellie
Booked3 Jan 2026
StartedTue 10 Feb
Handed over9 Mar 2026
Retention5% held to the end of defects
Timeline
Handed over and closed
Gareth · 9 Mar 15:00
Andy Rees Electrical: Electrics, second fix, £2,259.29
Andy Rees · 27 Feb 17:00
Jon Haskins Plumbing and Heating: Plumbing, second fix, £1,697.17
Jon Haskins · 27 Feb 17:00
Nick Weller Flooring: Floor laying, supply-laid by the floor layer, £1,697.17
Nick Weller · 25 Feb 17:00
Delivered: Flooring from Cotsmoor Flooring Trade (PO-5188, £2,093.97)
Dave Kerr · 25 Feb 08:15
Delivered: Counter worktops, templated and fitted from Halbrook Worktops (PO-5173, £2,257.06)
Dave Kerr · 23 Feb 08:15
Lee Carver Tiling: Tiling, tiling, £1,686.36
Lee Carver · 20 Feb 17:00
Delivered: Wall tiles and adhesive from Brackwell Tiles (PO-5174, £1,780.24)
Dave Kerr · 17 Feb 08:15
Andy Rees Electrical: Electrics, first fix, £2,259.29
Andy Rees · 12 Feb 17:00
Jon Haskins Plumbing and Heating: Plumbing, first fix, £1,697.17
Jon Haskins · 12 Feb 17:00
Delivered: Joinery timber and sheet from Kestle Timber (PO-5168, £2,317.99)
Dave Kerr · 11 Feb 08:15
Delivered: Partitions, board and sundries from Avonmere Builders Merchants (PO-5170, £3,058.44)
Dave Kerr · 11 Feb 08:15
Delivered: Lighting and electrical from Voltmere Electrical Wholesale (PO-5171, £2,395.08)
Dave Kerr · 11 Feb 08:15
First day on site: Dave, Ellie, Sam, Tom
Site app · 10 Feb 07:30
Booked: £39,300 ex VAT
Owen · 3 Jan 11:00