LIVE DEMO
Bathroom · domestic · fixed price

Job 3965

Complete
Bathroom refit
For Jenny and Andrew Jarrett, Cotham. Crew B with Kate Lyons. On site 18 Mar to 23 Mar, handed over 28 Mar 2026.
Agreed price
£10,800
ex VAT
Final margin
20.7%
quoted 25.0%
100% of the work done19 m² tiled
Client's portal view
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
Quoted margin25.0%£2,702 on £10,800
Final margin20.7%£2,239 profit
Invoiced so far£10,800of £10,800, £10,800 paid
Where the money went
PersonHoursLabour costDifference
MT
Mike Tanner
Lead fitter and tiler, crew B, £34/h at cost
32 h
of 32 h estimated
£1,088
of £1,088
on budget
RH
Ryan Hale
Fitter, crew B, £30/h at cost
32 h
of 28 h estimated
£960
of £840
+£120
CW
Callum Webb
Apprentice fitter, crew B, £16/h at cost
24 h
of 20 h estimated
£384
of £320
+£64
True labour cost. The 25 bathrooms finished this year really took 4.5 h per m² tiled, against the old rule of 4.2. This job: 19 m² tiled, priced on 80 h. Rule of thumb: 4.2 h per m² tiled. New quotes now use the true rate →
Cost week by week
£8,561 spent over 2 weeks, against a £8,098 estimate
LabourMaterialsSubcontract
Extras and variations · 0
Variations →
No extras on this job.
Timesheets · 88 h, £2,432 at cost
Timesheets →
Week ofPersonHoursCostStatus
23 Mar
Tap for the days
CWCallum Webb8 h
1 day
£128.00
at £16/h
approved
from the paper sheets
23 Mar
Tap for the days
MTMike Tanner8 h
1 day
£272.00
at £34/h
approved
from the paper sheets
23 Mar
Tap for the days
RHRyan Hale8 h
1 day
£240.00
at £30/h
approved
from the paper sheets
16 Mar
Tap for the days
CWCallum Webb16 h
2 days
£256.00
at £16/h
approved
from the paper sheets
16 Mar
Tap for the days
MTMike Tanner24 h
3 days
£816.00
at £34/h
approved
from the paper sheets
16 Mar
Tap for the days
RHRyan Hale24 h
3 days
£720.00
at £30/h
approved
from the paper sheets
Purchases · 5, £4,079
Purchases →
OrderWhatStatusNet
PO-5223
Avonmere Builders Merchants, raised 15 Mar
Board, tanking and sundriesDelivered 18 Mar, billed£532.96
PO-5224
Voltmere Electrical Wholesale, raised 15 Mar
Lighting and extractorDelivered 18 Mar, billed£199.74
PO-5220
Brackwell Tiles, raised 14 Mar
Wall and floor tiles, adhesive, groutDelivered 19 Mar, billed£1,078.59
PO-5221
Kestle Timber, raised 14 Mar
Timber and fixingsDelivered 18 Mar, billed£297.13
PO-5211
Linmouth Bathroom Supply, raised 8 Mar
Sanitaryware and brasswareDelivered 17 Mar, billed£1,970.33
Subcontractor invoices · 5, £2,050
Tap one for the subcontractor
InvoiceWorkStatusAmount
SC-3508
Jon Haskins Plumbing and Heating, 23 Mar
Plumbing, second fixPaid£635.00
SC-3509
Gary Pullen Electrical, 23 Mar
Electrics, second fixPaid£185.00
SC-3507
Mark Dent Plastering, 19 Mar
Plastering, skim and making goodPaid£410.00
SC-3504
Jon Haskins Plumbing and Heating, 18 Mar
Plumbing, first fixPaid£635.00
SC-3505
Gary Pullen Electrical, 18 Mar
Electrics, first fixPaid£185.00
Invoices · posted to Xero when sent
Billing →
InvoiceStageStatusNetGrossXero
INV-2249
issued 16 Feb
Deposit
1 line
Paid 1 Mar£2,700.00£3,240.00posted
INV-2279
issued 20 Mar
Progress
1 line
Paid 26 Mar£5,400.00£6,480.00posted
INV-2285
issued 30 Mar
Completion
1 line
Paid 7 Apr£2,700.00£3,240.00posted
Stages £10,800 + billed extras £0 = £10,800 on invoices. £10,800 sent, £10,800 paid.
JA
Jenny and Andrew Jarrett
Jenny Jarrett · client since 17 Jan 2026
Site48 Victoria Walk, Cotham
Phone07700 900464
PortalLive: progress, extras, invoices
See what Jenny sees in the portal
Messages in the portal
No messages on this job yet.
People and dates
Project managerKate Lyons
CrewCrew B: Mike, Ryan, Callum
Booked14 Feb 2026
StartedWed 18 Mar
Handed over28 Mar 2026
Timeline
Handed over and closed
Kate · 28 Mar 15:00
Jon Haskins Plumbing and Heating: Plumbing, second fix, £635.00
Jon Haskins · 23 Mar 17:00
Gary Pullen Electrical: Electrics, second fix, £185.00
Gary Pullen · 23 Mar 17:00
Mark Dent Plastering: Plastering, skim and making good, £410.00
Mark Dent · 19 Mar 17:00
Jon Haskins Plumbing and Heating: Plumbing, first fix, £635.00
Jon Haskins · 18 Mar 17:00
Gary Pullen Electrical: Electrics, first fix, £185.00
Gary Pullen · 18 Mar 17:00
First day on site: Mike, Ryan
Site app · 18 Mar 07:30
Booked: £10,800 ex VAT
Owen · 14 Feb 11:00