LIVE DEMO
Bathroom · domestic · fixed price

Job 3970

Complete
Family bathroom
For Elaine and Martin Chapman, Cotham. Crew B with Kate Lyons. On site 9 Apr to 13 Apr, handed over 16 Apr 2026.
Agreed price
£9,050
ex VAT
Final margin
18.2%
quoted 25.0%
100% of the work done13 m² tiled
Client's portal view
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
Quoted margin25.0%£2,266 on £9,050
Final margin18.2%£1,649 profit
Invoiced so far£9,050of £9,050, £9,050 paid
Where the money went
PersonHoursLabour costDifference
MT
Mike Tanner
Lead fitter and tiler, crew B, £34/h at cost
24 h
of 22 h estimated
£816
of £748
+£68
RH
Ryan Hale
Fitter, crew B, £30/h at cost
24 h
of 19 h estimated
£720
of £570
+£150
CW
Callum Webb
Apprentice fitter, crew B, £16/h at cost
24 h
of 13.5 h estimated
£384
of £216
+£168
True labour cost. The 25 bathrooms finished this year really took 4.5 h per m² tiled, against the old rule of 4.2. This job: 13 m² tiled, priced on 54.5 h. Rule of thumb: 4.2 h per m² tiled. New quotes now use the true rate →
Cost week by week
£7,401 spent over 2 weeks, against a £6,784 estimate
LabourMaterialsSubcontract
Extras and variations · 0
Variations →
No extras on this job.
Timesheets · 72 h, £1,920 at cost
Timesheets →
Week ofPersonHoursCostStatus
13 Apr
Tap for the days
CWCallum Webb8 h
1 day
£128.00
at £16/h
approved
from the paper sheets
13 Apr
Tap for the days
MTMike Tanner8 h
1 day
£272.00
at £34/h
approved
from the paper sheets
13 Apr
Tap for the days
RHRyan Hale8 h
1 day
£240.00
at £30/h
approved
from the paper sheets
6 Apr
Tap for the days
CWCallum Webb16 h
2 days
£256.00
at £16/h
approved
from the paper sheets
6 Apr
Tap for the days
MTMike Tanner16 h
2 days
£544.00
at £34/h
approved
from the paper sheets
6 Apr
Tap for the days
RHRyan Hale16 h
2 days
£480.00
at £30/h
approved
from the paper sheets
Purchases · 5, £3,581
Purchases →
OrderWhatStatusNet
PO-5247
Voltmere Electrical Wholesale, raised 6 Apr
Lighting and extractorDelivered 9 Apr, billed£186.53
PO-5250
Avonmere Builders Merchants, raised 6 Apr
Board, tanking and sundriesDelivered 9 Apr, billed£464.73
PO-5244
Brackwell Tiles, raised 5 Apr
Wall and floor tiles, adhesive, groutDelivered 10 Apr, billed£969.39
PO-5245
Kestle Timber, raised 5 Apr
Timber and fixingsDelivered 9 Apr, billed£247.64
PO-5242
Linmouth Bathroom Supply, raised 30 Mar
Sanitaryware and brasswareDelivered 8 Apr, billed£1,713.09
Subcontractor invoices · 5, £1,900
Tap one for the subcontractor
InvoiceWorkStatusAmount
SC-3534
Jon Haskins Plumbing and Heating, 13 Apr
Plumbing, second fixPaid£590.00
SC-3535
Gary Pullen Electrical, 13 Apr
Electrics, second fixPaid£170.00
SC-3532
Mark Dent Plastering, 10 Apr
Plastering, skim and making goodPaid£380.00
SC-3530
Jon Haskins Plumbing and Heating, 9 Apr
Plumbing, first fixPaid£590.00
SC-3531
Gary Pullen Electrical, 9 Apr
Electrics, first fixPaid£170.00
Invoices · posted to Xero when sent
Billing →
InvoiceStageStatusNetGrossXero
INV-2263
issued 4 Mar
Deposit
1 line
Paid 13 Mar£2,262.50£2,715.00posted
INV-2295
issued 13 Apr
Progress
1 line
Paid 23 Apr£4,525.00£5,430.00posted
INV-2301
issued 17 Apr
Completion
1 line
Paid 25 Apr£2,262.50£2,715.00posted
Stages £9,050 + billed extras £0 = £9,050 on invoices. £9,050 sent, £9,050 paid.
EM
Elaine and Martin Chapman
Elaine Chapman · client since 8 Feb 2026
Site33 Park Avenue, Cotham
Phone07700 900500
PortalLive: progress, extras, invoices
See what Elaine sees in the portal
Messages in the portal
No messages on this job yet.
People and dates
Project managerKate Lyons
CrewCrew B: Mike, Ryan, Callum
Booked2 Mar 2026
StartedThu 9 Apr
Handed over16 Apr 2026
Timeline
Handed over and closed
Kate · 16 Apr 15:00
Jon Haskins Plumbing and Heating: Plumbing, second fix, £590.00
Jon Haskins · 13 Apr 17:00
Gary Pullen Electrical: Electrics, second fix, £170.00
Gary Pullen · 13 Apr 17:00
Mark Dent Plastering: Plastering, skim and making good, £380.00
Mark Dent · 10 Apr 17:00
Jon Haskins Plumbing and Heating: Plumbing, first fix, £590.00
Jon Haskins · 9 Apr 17:00
Gary Pullen Electrical: Electrics, first fix, £170.00
Gary Pullen · 9 Apr 17:00
First day on site: Callum, Mike, Ryan
Site app · 9 Apr 07:30
Booked: £9,050 ex VAT
Owen · 2 Mar 11:00