LIVE DEMO
Kitchen · domestic · fixed price

Job 3975

Complete
Kitchen and utility fit-out
For Hannah and Adam Merrick, Cotham. Crew A with Kate Lyons. On site 13 May to 27 May, handed over 31 May 2026.
Agreed price
£25,550
ex VAT
Final margin
20.1%
quoted 24.8%
100% of the work done17 cabinets
Client's portal view
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
Quoted margin24.8%£6,344 on £25,550
Final margin20.1%£5,131 profit
Invoiced so far£25,550of £25,550, £25,550 paid
Where the money went
PersonHoursLabour costDifference
SR
Steve Rowe
Lead fitter, crew A, £34/h at cost
72 h
of 68.5 h estimated
£2,448
of £2,329
+£119
LD
Liam Doyle
Joiner, crew A, £30/h at cost
72 h
of 68.5 h estimated
£2,160
of £2,055
+£105
JP
Josh Penrose
Apprentice joiner, crew A, £16/h at cost
56 h
of 43 h estimated
£896
of £688
+£208
RF
Rob Finch
Decorator, £28/h at cost
16 h
of 15.5 h estimated
£448
of £434
+£14
True labour cost. The 15 kitchens finished this year really took 12.95 h per cabinet, against the old rule of 11.5. This job: 17 cabinets, priced on 195.5 h. Rule of thumb: 11.5 h per cabinet. New quotes now use the true rate →
Cost week by week
£20,419 spent over 3 weeks, against a £19,206 estimate
LabourMaterialsSubcontract
Extras and variations · 0
Variations →
No extras on this job.
Timesheets · 216 h, £5,952 at cost
Timesheets →
Week ofPersonHoursCostStatus
25 May
Tap for the days
JPJosh Penrose8 h
1 day
£128.00
at £16/h
approved
from the paper sheets
25 May
Tap for the days
LDLiam Doyle8 h
1 day
£240.00
at £30/h
approved
from the paper sheets
25 May
Tap for the days
RFRob Finch16 h
2 days
£448.00
at £28/h
approved
from the paper sheets
25 May
Tap for the days
SRSteve Rowe8 h
1 day
£272.00
at £34/h
approved
from the paper sheets
18 May
Tap for the days
JPJosh Penrose32 h
4 days
£512.00
at £16/h
approved
from the paper sheets
18 May
Tap for the days
LDLiam Doyle40 h
5 days
£1,200.00
at £30/h
approved
from the paper sheets
18 May
Tap for the days
SRSteve Rowe40 h
5 days
£1,360.00
at £34/h
approved
from the paper sheets
11 May
Tap for the days
JPJosh Penrose16 h
2 days
£256.00
at £16/h
approved
from the paper sheets
11 May
Tap for the days
LDLiam Doyle24 h
3 days
£720.00
at £30/h
approved
from the paper sheets
11 May
Tap for the days
SRSteve Rowe24 h
3 days
£816.00
at £34/h
approved
from the paper sheets
Purchases · 6, £11,317
Purchases →
OrderWhatStatusNet
PO-5301
Brackwell Tiles, raised 14 May
Splashback tiles and adhesiveDelivered 19 May, billed£461.55
PO-5299
Avonmere Builders Merchants, raised 11 May
Plaster, board and sundriesDelivered 14 May, billed£460.24
PO-5300
Voltmere Electrical Wholesale, raised 11 May
Lighting and electrical fittingsDelivered 14 May, billed£443.61
PO-5294
Halbrook Worktops, raised 10 May
Worktops, templated and fittedDelivered 22 May, billed£3,172.13
PO-5295
Kestle Timber, raised 10 May
Timber, panels and fixingsDelivered 14 May, billed£353.83
PO-5269
Wrenfold Kitchen Supply, raised 20 Apr
Kitchen units and doorsDelivered 12 May, billed£6,425.56
Subcontractor invoices · 5, £3,150
Tap one for the subcontractor
InvoiceWorkStatusAmount
SC-3589
Gary Pullen Electrical, 27 May
Electrics, second fixPaid£710.00
SC-3590
Jon Haskins Plumbing and Heating, 27 May
Plumbing, second fixPaid£520.00
SC-3579
Mark Dent Plastering, 19 May
Plastering, skim and making goodPaid£690.00
SC-3575
Jon Haskins Plumbing and Heating, 15 May
Plumbing, first fixPaid£520.00
SC-3573
Gary Pullen Electrical, 14 May
Electrics, first fixPaid£710.00
Invoices · posted to Xero when sent
Billing →
InvoiceStageStatusNetGrossXero
INV-2283
issued 26 Mar
Deposit
1 line
Paid 2 Apr£6,387.50£7,665.00posted
INV-2326
issued 20 May
Progress
1 line
Paid 3 Jun£12,775.00£15,330.00posted
INV-2334
issued 1 Jun
Completion
1 line
Paid 17 Jun£6,387.50£7,665.00posted
Stages £25,550 + billed extras £0 = £25,550 on invoices. £25,550 sent, £25,550 paid.
HA
Hannah and Adam Merrick
Hannah Merrick · client since 14 Mar 2026
Site96 Belmont Avenue, Cotham
Phone07700 900166
PortalLive: progress, extras, invoices
See what Hannah sees in the portal
Messages in the portal
No messages on this job yet.
People and dates
Project managerKate Lyons
CrewCrew A: Steve, Liam, Josh
Booked24 Mar 2026
StartedWed 13 May
Handed over31 May 2026
Timeline
Handed over and closed
Kate · 31 May 15:00
Gary Pullen Electrical: Electrics, second fix, £710.00
Gary Pullen · 27 May 17:00
Jon Haskins Plumbing and Heating: Plumbing, second fix, £520.00
Jon Haskins · 27 May 17:00
Mark Dent Plastering: Plastering, skim and making good, £690.00
Mark Dent · 19 May 17:00
Jon Haskins Plumbing and Heating: Plumbing, first fix, £520.00
Jon Haskins · 15 May 17:00
Gary Pullen Electrical: Electrics, first fix, £710.00
Gary Pullen · 14 May 17:00
First day on site: Liam, Steve
Site app · 13 May 07:30
Booked: £25,550 ex VAT
Owen · 24 Mar 11:00