Café · commercial · fixed price

Job 3978

Complete
Café refit: counter and seating
For Larkspur Kitchen, Bristol. Crew C with Gareth Price. On site 8 May to 19 May, handed over 28 May 2026.
Agreed price
£32,150
ex VAT
Final margin
22.0%
quoted 23.0%
100% of the work done77 m² floor
Client's portal view
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
Quoted margin23.0%£7,396 on £32,150
Final margin22.0%£7,083 profit
Invoiced so far£32,150of £32,150, £30,542 paid, £1,608 retention held
Where the money went
PersonHoursLabour costDifference
DK
Dave Kerr
Lead fitter, crew C, £35/h at cost
64 h
of 60 h estimated
£2,240
of £2,100
+£140
TA
Tom Ashby
Joiner, crew C, £30/h at cost
64 h
of 60 h estimated
£1,920
of £1,800
+£120
ER
Ellie Rudd
Apprentice joiner, crew C, £16/h at cost
56 h
of 44 h estimated
£896
of £704
+£192
RF
Rob Finch
Decorator, £28/h at cost
16 h
of 18 h estimated
£448
of £504
-£56
SK
Sam Kerridge
Labourer and driver, £22/h at cost
16 h
of 18 h estimated
£352
of £396
-£44
True labour cost. The 3 cafés finished this year really took 2.81 h per m² of floor, against the old rule of 2.6. This job: 77 m² floor, priced on 200 h. Rule of thumb: 2.6 h per m² of floor. New quotes now use the true rate →
Cost week by week
£25,067 spent over 3 weeks, against a £24,754 estimate
LabourMaterialsSubcontract
Extras and variations · 0
Variations →
No extras on this job.
Timesheets · 216 h, £5,856 at cost
Timesheets →
Week ofPersonHoursCostStatus
18 May
Tap for the days
DKDave Kerr16 h
2 days
£560.00
at £35/h
approved
from the paper sheets
18 May
Tap for the days
EREllie Rudd16 h
2 days
£256.00
at £16/h
approved
from the paper sheets
18 May
Tap for the days
RFRob Finch16 h
2 days
£448.00
at £28/h
approved
from the paper sheets
18 May
Tap for the days
TATom Ashby16 h
2 days
£480.00
at £30/h
approved
from the paper sheets
11 May
Tap for the days
DKDave Kerr40 h
5 days
£1,400.00
at £35/h
approved
from the paper sheets
11 May
Tap for the days
EREllie Rudd32 h
4 days
£512.00
at £16/h
approved
from the paper sheets
11 May
Tap for the days
SKSam Kerridge8 h
1 day
£176.00
at £22/h
approved
from the paper sheets
11 May
Tap for the days
TATom Ashby40 h
5 days
£1,200.00
at £30/h
approved
from the paper sheets
4 May
Tap for the days
DKDave Kerr8 h
1 day
£280.00
at £35/h
approved
from the paper sheets
4 May
Tap for the days
EREllie Rudd8 h
1 day
£128.00
at £16/h
approved
from the paper sheets
4 May
Tap for the days
SKSam Kerridge8 h
1 day
£176.00
at £22/h
approved
from the paper sheets
4 May
Tap for the days
TATom Ashby8 h
1 day
£240.00
at £30/h
approved
from the paper sheets
Purchases · 6, £10,761
Purchases →
OrderWhatStatusNet
PO-5298
Cotsmoor Flooring Trade, raised 11 May
FlooringDelivered 18 May, billed£1,650.31
PO-5291
Brackwell Tiles, raised 8 May
Wall tiles and adhesiveDelivered 13 May, billed£1,423.78
PO-5288
Voltmere Electrical Wholesale, raised 5 May
Lighting and electricalDelivered 8 May, billed£1,804.12
PO-5289
Avonmere Builders Merchants, raised 5 May
Partitions, board and sundriesDelivered 8 May, billed£2,314.85
PO-5285
Kestle Timber, raised 4 May
Joinery timber and sheetDelivered 8 May, billed£1,816.63
PO-5284
Halbrook Worktops, raised 3 May
Counter worktops, templated and fittedDelivered 15 May, billed£1,751.40
Subcontractor invoices · 6, £8,450
Tap one for the subcontractor
InvoiceWorkStatusAmount
SC-3580
Andy Rees Electrical, 19 May
Electrics, second fixPaid£1,690.00
SC-3581
Jon Haskins Plumbing and Heating, 19 May
Plumbing, second fixPaid£1,270.00
SC-3578
Nick Weller Flooring, 18 May
Floor laying, supply-laid by the floor layerPaid£1,270.00
SC-3574
Lee Carver Tiling, 14 May
Tiling, tilingPaid£1,260.00
SC-3569
Andy Rees Electrical, 11 May
Electrics, first fixPaid£1,690.00
SC-3570
Jon Haskins Plumbing and Heating, 11 May
Plumbing, first fixPaid£1,270.00
Invoices · posted to Xero when sent
Billing →
InvoiceStageStatusNetGrossXero
INV-2291
issued 1 Apr
Deposit
1 line
Paid 2 May£8,037.50£9,162.74
£402 retention held
posted
INV-2322
issued 13 May
Progress
1 line
Paid 31 May£16,075.00£18,325.50
£804 retention held
posted
INV-2332
issued 29 May
Completion
1 line
Paid 25 Jun£8,037.50£9,162.74
£402 retention held
posted
Stages £32,150 + billed extras £0 = £32,150 on invoices. £32,150 sent, £30,542 paid, £1,608 retention held until the defects period ends.
LK
Larkspur Kitchen
Contact: Patrick Wakefield · client since 9 Mar 2026
Site14 North Street, Bristol
Phone0117 496 0968
PortalLive: progress, extras, invoices
See what Patrick sees in the portal
Messages in the portal
No messages on this job yet.
People and dates
Project managerGareth Price
CrewCrew C: Dave, Tom, Ellie
Booked30 Mar 2026
StartedFri 8 May
Handed over28 May 2026
Retention5% held to the end of defects
Timeline
Handed over and closed
Gareth · 28 May 15:00
Andy Rees Electrical: Electrics, second fix, £1,690.00
Andy Rees · 19 May 17:00
Jon Haskins Plumbing and Heating: Plumbing, second fix, £1,270.00
Jon Haskins · 19 May 17:00
Nick Weller Flooring: Floor laying, supply-laid by the floor layer, £1,270.00
Nick Weller · 18 May 17:00
Lee Carver Tiling: Tiling, tiling, £1,260.00
Lee Carver · 14 May 17:00
Andy Rees Electrical: Electrics, first fix, £1,690.00
Andy Rees · 11 May 17:00
Jon Haskins Plumbing and Heating: Plumbing, first fix, £1,270.00
Jon Haskins · 11 May 17:00
First day on site: Dave, Ellie, Sam, Tom
Site app · 8 May 07:30
Booked: £32,150 ex VAT
Owen · 30 Mar 11:00