Bathroom · domestic · fixed price

Job 3987

Complete
Bathroom and en-suite
For Jane Chivers, Bishopston. Crew B with Kate Lyons. On site 8 Jun to 10 Jun, handed over 15 Jun 2026.
Agreed price
£10,050
ex VAT, +£530 extras billed
Final margin
28.9%
quoted 25.4%
100% of the work done16 m² tiled
Client's portal view
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
Extras captured on site
1 extra on this job
Every extra ↓
Quoted margin25.4%£2,555 on £10,050
Final margin28.9%£3,061 profit
Invoiced so far£10,580of £10,580, £10,580 paid
Where the money went
PersonHoursLabour costDifference
MT
Mike Tanner
Lead fitter and tiler, crew B, £34/h at cost
24 h
of 27 h estimated
£816
of £918
-£102
RH
Ryan Hale
Fitter, crew B, £30/h at cost
24 h
of 23.5 h estimated
£720
of £705
+£15
CW
Callum Webb
Apprentice fitter, crew B, £16/h at cost
16 h
of 17 h estimated
£256
of £272
-£16
True labour cost. The 25 bathrooms finished this year really took 4.5 h per m² tiled, against the old rule of 4.2. This job: 16 m² tiled, priced on 67.5 h. Rule of thumb: 4.2 h per m² tiled. New quotes now use the true rate →
Cost week by week
£7,519 spent over 2 weeks, against a £7,495 estimate
LabourMaterialsSubcontract
Extras and variations · 1
Variations →
Timesheets · 64 h, £1,792 at cost
Timesheets →
Week ofPersonHoursCostStatus
8 Jun
Tap for the days
CWCallum Webb16 h
2 days
£256.00
at £16/h
approved
8 Jun
Tap for the days
MTMike Tanner24 h
3 days
£816.00
at £34/h
approved
8 Jun
Tap for the days
RHRyan Hale24 h
3 days
£720.00
at £30/h
approved
Purchases · 5, £3,727
Purchases →
OrderWhatStatusNet
PO-5330
Avonmere Builders Merchants, raised 5 Jun
Board, tanking and sundriesDelivered 8 Jun, billed£482.19
PO-5331
Voltmere Electrical Wholesale, raised 5 Jun
Lighting and extractorDelivered 8 Jun, billed£193.77
PO-5328
Kestle Timber, raised 4 Jun
Timber and fixingsDelivered 8 Jun, billed£257.52
PO-5329
Brackwell Tiles, raised 4 Jun
Wall and floor tiles, adhesive, groutDelivered 9 Jun, billed£1,013.75
PO-5320
Linmouth Bathroom Supply, raised 27 May
Sanitaryware and brasswareDelivered 5 Jun, billed£1,779.74
Subcontractor invoices · 5, £2,000
Tap one for the subcontractor
InvoiceWorkStatusAmount
SC-3612
Jon Haskins Plumbing and Heating, 10 Jun
Plumbing, second fixPaid£620.00
SC-3613
Gary Pullen Electrical, 10 Jun
Electrics, second fixPaid£180.00
SC-3610
Mark Dent Plastering, 9 Jun
Plastering, skim and making goodPaid£400.00
SC-3603
Jon Haskins Plumbing and Heating, 8 Jun
Plumbing, first fixPaid£620.00
SC-3604
Gary Pullen Electrical, 8 Jun
Electrics, first fixPaid£180.00
Invoices · posted to Xero when sent
Billing →
InvoiceStageStatusNetGrossXero
INV-2318
issued 11 May
Deposit
1 line
Paid 24 May£2,512.50£3,015.00posted
INV-2346
issued 9 Jun
Progress
1 line
Paid 18 Jun£5,025.00£6,030.00posted
INV-2354
issued 16 Jun
Completion
2 lines, with V-3987-1
Paid 28 Jun£3,042.50£3,651.00posted
Stages £10,050 + billed extras £530 = £10,580 on invoices. £10,580 sent, £10,580 paid.
JC
Jane Chivers
Jane Chivers · client since 9 Apr 2026
Site40 Beech Grove, Bishopston
Phone07700 900678
PortalLive: progress, extras, invoices
See what Jane sees in the portal
Messages in the portal
No messages on this job yet.
People and dates
Project managerKate Lyons
CrewCrew B: Mike, Ryan, Callum
Booked7 May 2026
StartedMon 8 Jun
Handed over15 Jun 2026
Timeline
Handed over and closed
Kate · 15 Jun 15:00
Jon Haskins Plumbing and Heating: Plumbing, second fix, £620.00
Jon Haskins · 10 Jun 17:00
Gary Pullen Electrical: Electrics, second fix, £180.00
Gary Pullen · 10 Jun 17:00
Mark Dent Plastering: Plastering, skim and making good, £400.00
Mark Dent · 9 Jun 17:00
Jon Haskins Plumbing and Heating: Plumbing, first fix, £620.00
Jon Haskins · 8 Jun 17:00
Gary Pullen Electrical: Electrics, first fix, £180.00
Gary Pullen · 8 Jun 17:00
First day on site: Callum, Mike, Ryan
Site app · 8 Jun 07:30
Booked: £10,050 ex VAT
Owen · 7 May 11:00