Bathroom · domestic · fixed price

Job 4001

Complete
Family bathroom
For Gemma and Will Moxham, Keynsham. Crew B with Kate Lyons. On site 20 Jul to 22 Jul, handed over 26 Jul 2026.
Agreed price
£9,850
ex VAT
Final margin
23.6%
quoted 23.9%
100% of the work done16 m² tiled
Client's portal view
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
Quoted margin23.9%£2,355 on £9,850
Final margin23.6%£2,321 profit
Invoiced so far£9,850of £9,850, £9,850 paid
Where the money went
PersonHoursLabour costDifference
MT
Mike Tanner
Lead fitter and tiler, crew B, £34/h at cost
24 h
of 27 h estimated
£816
of £918
-£102
RH
Ryan Hale
Fitter, crew B, £30/h at cost
24 h
of 23.5 h estimated
£720
of £705
+£15
CW
Callum Webb
Apprentice fitter, crew B, £16/h at cost
16 h
of 17 h estimated
£256
of £272
-£16
True labour cost. The 25 bathrooms finished this year really took 4.5 h per m² tiled, against the old rule of 4.2. This job: 16 m² tiled, priced on 67.5 h. Rule of thumb: 4.2 h per m² tiled. New quotes now use the true rate →
Cost week by week
£7,529 spent over 2 weeks, against a £7,495 estimate
LabourMaterialsSubcontract
Extras and variations · 0
Variations →
No extras on this job.
Timesheets · 64 h, £1,792 at cost
Timesheets →
Week ofPersonHoursCostStatus
20 Jul
Tap for the days
CWCallum Webb16 h
2 days
£256.00
at £16/h
approved
20 Jul
Tap for the days
MTMike Tanner24 h
3 days
£816.00
at £34/h
approved
20 Jul
Tap for the days
RHRyan Hale24 h
3 days
£720.00
at £30/h
approved
Purchases · 5, £3,737
Purchases →
OrderWhatStatusNet
PO-5401
Voltmere Electrical Wholesale, raised 17 Jul
Lighting and extractorDelivered 20 Jul, billed£186.43
PO-5405
Avonmere Builders Merchants, raised 17 Jul
Board, tanking and sundriesDelivered 20 Jul, billed£496.77
PO-5395
Kestle Timber, raised 16 Jul
Timber and fixingsDelivered 20 Jul, billed£256.77
PO-5399
Brackwell Tiles, raised 16 Jul
Wall and floor tiles, adhesive, groutDelivered 21 Jul, billed£982.02
PO-5388
Linmouth Bathroom Supply, raised 8 Jul
Sanitaryware and brasswareDelivered 17 Jul, billed£1,814.74
Subcontractor invoices · 5, £2,000
Tap one for the subcontractor
InvoiceWorkStatusAmount
SC-3676
Jon Haskins Plumbing and Heating, 22 Jul
Plumbing, second fixPaid£620.00
SC-3677
Gary Pullen Electrical, 22 Jul
Electrics, second fixPaid£180.00
SC-3674
Mark Dent Plastering, 21 Jul
Plastering, skim and making goodPaid£400.00
SC-3669
Jon Haskins Plumbing and Heating, 20 Jul
Plumbing, first fixPaid£620.00
SC-3670
Gary Pullen Electrical, 20 Jul
Electrics, first fixPaid£180.00
Invoices · posted to Xero when sent
Billing →
InvoiceStageStatusNetGrossXero
INV-2353
issued 15 Jun
Deposit
1 line
Paid 1 Jul£2,462.50£2,955.00posted
INV-2387
issued 21 Jul
Progress
1 line
Paid 5 Aug£4,925.00£5,910.00posted
INV-2393
issued 27 Jul
Completion
1 line
Paid 2 Aug£2,462.50£2,955.00posted
Stages £9,850 + billed extras £0 = £9,850 on invoices. £9,850 sent, £9,850 paid.
GW
Gemma and Will Moxham
Gemma Moxham · client since 21 May 2026
Site67 Kingsley Road, Keynsham
Phone07700 900496
PortalLive: progress, extras, invoices
See what Gemma sees in the portal
Messages in the portal
No messages on this job yet.
People and dates
Project managerKate Lyons
CrewCrew B: Mike, Ryan, Callum
Booked13 Jun 2026
StartedMon 20 Jul
Handed over26 Jul 2026
Timeline
Handed over and closed
Kate · 26 Jul 15:00
Jon Haskins Plumbing and Heating: Plumbing, second fix, £620.00
Jon Haskins · 22 Jul 17:00
Gary Pullen Electrical: Electrics, second fix, £180.00
Gary Pullen · 22 Jul 17:00
Mark Dent Plastering: Plastering, skim and making good, £400.00
Mark Dent · 21 Jul 17:00
Jon Haskins Plumbing and Heating: Plumbing, first fix, £620.00
Jon Haskins · 20 Jul 17:00
Gary Pullen Electrical: Electrics, first fix, £180.00
Gary Pullen · 20 Jul 17:00
First day on site: Callum, Mike, Ryan
Site app · 20 Jul 07:30
Booked: £9,850 ex VAT
Owen · 13 Jun 11:00