Bathroom · domestic · fixed price
Job 4001
CompleteFamily bathroom
For Gemma and Will Moxham, Keynsham. Crew B with Kate Lyons. On site 20 Jul to 22 Jul, handed over 26 Jul 2026.
Agreed price
£9,850
ex VAT
Final margin
23.6%
quoted 23.9%
100% of the work done16 m² tiled
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
CostEstimateActual so farFinalDifference
Labour64 h logged against 67.5 h estimated, at each person's true cost rate£1,895£1,792£1,792-£1035.4% underMaterials5 purchases received£3,600£3,737£3,737+£1373.8% overSubcontract5 invoices from the plumber, electrician and plasterer£2,000£2,000£2,000On budgetTotal cost£7,495£7,529£7,529+£340.5% overQuoted margin23.9%£2,355 on £9,850
Final margin23.6%£2,321 profit
Invoiced so far£9,850of £9,850, £9,850 paid
Where the money went
| Person | Hours | Labour cost | Difference |
|---|---|---|---|
MT Mike Tanner Lead fitter and tiler, crew B, £34/h at cost | 24 h of 27 h estimated | £816 of £918 | -£102 |
RH Ryan Hale Fitter, crew B, £30/h at cost | 24 h of 23.5 h estimated | £720 of £705 | +£15 |
CW Callum Webb Apprentice fitter, crew B, £16/h at cost | 16 h of 17 h estimated | £256 of £272 | -£16 |
True labour cost. The 25 bathrooms finished this year really took 4.5 h per m² tiled, against the old rule of 4.2. This job: 16 m² tiled, priced on 67.5 h. Rule of thumb: 4.2 h per m² tiled. New quotes now use the true rate →
| Estimate line | Estimate | Ordered | Received | Difference |
|---|---|---|---|---|
Sanitaryware and brassware Linmouth Bathroom Supply, PO-5388 | £1,730 | £1,815 | £1,815 | +£85 |
Wall and floor tiles, adhesive, grout Brackwell Tiles, PO-5399 | £970 | £982 | £982 | +£12 |
Board, tanking and sundries Avonmere Builders Merchants, PO-5405 | £470 | £497 | £497 | +£27 |
Lighting and extractor Voltmere Electrical Wholesale, PO-5401 | £180 | £186 | £186 | +£6 |
Timber and fixings Kestle Timber, PO-5395 | £250 | £257 | £257 | +£7 |
Materials count when they are delivered and signed for on site. Nothing is on order and not received. Supplier bills post to Xero from here.
| Trade | Agreed | Invoiced | Difference |
|---|---|---|---|
Plumbing Jon Haskins Plumbing and Heating, 2 invoices | £1,240 | £1,240 | on the agreed price |
Electrics Gary Pullen Electrical, 2 invoices | £360 | £360 | on the agreed price |
Plastering Mark Dent Plastering, 1 invoice | £400 | £400 | on the agreed price |
The forecast counts each trade at its agreed price until it invoices more.
Agreed price
stage invoices at 25%, 50% and 25%
£9,850.00
Revenue
£9,850.00
Labour
final
- £1,792.00
Materials
final
- £3,736.73
Subcontract
final
- £2,000.00
Profit
23.6% margin, quoted at 23.9% (£2,355)
£2,321.27
Cost week by week
£7,529 spent over 2 weeks, against a £7,495 estimate
LabourMaterialsSubcontract
| Week of | Hours | Labour | Materials | Subcontract | Total |
|---|---|---|---|---|---|
| 13 Jul | 0 h | £0 | £1,815 | £0 | £1,815 |
| 20 Jul | 64 h | £1,792 | £1,922 | £2,000 | £5,714 |
Extras and variations · 0
Variations →No extras on this job.
Timesheets · 64 h, £1,792 at cost
Timesheets →| Week of | Person | Hours | Cost | Status |
|---|---|---|---|---|
| 20 Jul Tap for the days Mon 20 Jul8 hTS-00895 Tue 21 Jul8 hTS-00906 | CWCallum Webb | 16 h 2 days | £256.00 at £16/h | approved |
| 20 Jul Tap for the days Mon 20 Jul8 hTS-00900 Tue 21 Jul8 hTS-00911 Wed 22 Jul8 hTS-00918 | MTMike Tanner | 24 h 3 days | £816.00 at £34/h | approved |
| 20 Jul Tap for the days Mon 20 Jul8 hTS-00901 Tue 21 Jul8 hTS-00912 Wed 22 Jul8 hTS-00919 | RHRyan Hale | 24 h 3 days | £720.00 at £30/h | approved |
Purchases · 5, £3,737
Purchases →| Order | What | Status | Net |
|---|---|---|---|
| PO-5401 Voltmere Electrical Wholesale, raised 17 Jul | Lighting and extractor | Delivered 20 Jul, billed | £186.43 |
| PO-5405 Avonmere Builders Merchants, raised 17 Jul | Board, tanking and sundries | Delivered 20 Jul, billed | £496.77 |
| PO-5395 Kestle Timber, raised 16 Jul | Timber and fixings | Delivered 20 Jul, billed | £256.77 |
| PO-5399 Brackwell Tiles, raised 16 Jul | Wall and floor tiles, adhesive, grout | Delivered 21 Jul, billed | £982.02 |
| PO-5388 Linmouth Bathroom Supply, raised 8 Jul | Sanitaryware and brassware | Delivered 17 Jul, billed | £1,814.74 |
Subcontractor invoices · 5, £2,000
Tap one for the subcontractor| Invoice | Work | Status | Amount |
|---|---|---|---|
| SC-3676 Jon Haskins Plumbing and Heating, 22 Jul | Plumbing, second fix | Paid | £620.00 |
Jon Haskins Plumbing and HeatingPlumber, Bedminster. Day rate £250. Insured to May 2027. Gas Safe registered. | |||
| SC-3677 Gary Pullen Electrical, 22 Jul | Electrics, second fix | Paid | £180.00 |
Gary Pullen ElectricalElectrician, Kingswood. Day rate £260. Insured to Mar 2027. Domestic jobs. Part P registered. | |||
| SC-3674 Mark Dent Plastering, 21 Jul | Plastering, skim and making good | Paid | £400.00 |
Mark Dent PlasteringPlasterer, Brislington. Day rate £220. Insured to Feb 2027. Skim and dry-lining. | |||
| SC-3669 Jon Haskins Plumbing and Heating, 20 Jul | Plumbing, first fix | Paid | £620.00 |
Jon Haskins Plumbing and HeatingPlumber, Bedminster. Day rate £250. Insured to May 2027. Gas Safe registered. | |||
| SC-3670 Gary Pullen Electrical, 20 Jul | Electrics, first fix | Paid | £180.00 |
Gary Pullen ElectricalElectrician, Kingswood. Day rate £260. Insured to Mar 2027. Domestic jobs. Part P registered. | |||
Invoices · posted to Xero when sent
Billing →| Invoice | Stage | Status | Net | Gross | Xero |
|---|---|---|---|---|---|
| INV-2353 issued 15 Jun | Deposit 1 line | Paid 1 Jul | £2,462.50 | £2,955.00 | posted |
| INV-2387 issued 21 Jul | Progress 1 line | Paid 5 Aug | £4,925.00 | £5,910.00 | posted |
| INV-2393 issued 27 Jul | Completion 1 line | Paid 2 Aug | £2,462.50 | £2,955.00 | posted |
Stages £9,850 + billed extras £0 = £9,850 on invoices. £9,850 sent, £9,850 paid.
Client
Client page →Gemma and Will Moxham
Gemma Moxham · client since 21 May 2026
Site67 Kingsley Road, Keynsham
Phone07700 900496
PortalLive: progress, extras, invoices
Messages in the portal
No messages on this job yet.
People and dates
Project managerKate Lyons
CrewCrew B: Mike, Ryan, Callum
Booked13 Jun 2026
StartedMon 20 Jul
Handed over26 Jul 2026
Timeline
Handed over and closed
Kate · 26 Jul 15:00
Jon Haskins Plumbing and Heating: Plumbing, second fix, £620.00
Jon Haskins · 22 Jul 17:00
Gary Pullen Electrical: Electrics, second fix, £180.00
Gary Pullen · 22 Jul 17:00
Mark Dent Plastering: Plastering, skim and making good, £400.00
Mark Dent · 21 Jul 17:00
Delivered: Wall and floor tiles, adhesive, grout from Brackwell Tiles (PO-5399, £982.02)
Mike Tanner · 21 Jul 08:15
Jon Haskins Plumbing and Heating: Plumbing, first fix, £620.00
Jon Haskins · 20 Jul 17:00
Gary Pullen Electrical: Electrics, first fix, £180.00
Gary Pullen · 20 Jul 17:00
Delivered: Timber and fixings from Kestle Timber (PO-5395, £256.77)
Mike Tanner · 20 Jul 08:15
Delivered: Lighting and extractor from Voltmere Electrical Wholesale (PO-5401, £186.43)
Mike Tanner · 20 Jul 08:15
Delivered: Board, tanking and sundries from Avonmere Builders Merchants (PO-5405, £496.77)
Mike Tanner · 20 Jul 08:15
First day on site: Callum, Mike, Ryan
Site app · 20 Jul 07:30
Delivered: Sanitaryware and brassware from Linmouth Bathroom Supply (PO-5388, £1,814.74)
Mike Tanner · 17 Jul 08:15
Booked: £9,850 ex VAT
Owen · 13 Jun 11:00