Bathroom · domestic · fixed price

Job 4010

Complete
Bathroom refit
For Henry Cleeve, Portishead. Crew B with Kate Lyons. On site 17 Aug to 20 Aug, handed over 25 Aug 2026.
Agreed price
£11,900
ex VAT
Final margin
27.6%
quoted 26.0%
100% of the work done22 m² tiled
Client's portal view
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
Quoted margin26.0%£3,099 on £11,900
Final margin27.6%£3,284 profit
Invoiced so far£11,900of £11,900, £11,900 paid
Where the money went
PersonHoursLabour costDifference
MT
Mike Tanner
Lead fitter and tiler, crew B, £34/h at cost
32 h
of 37 h estimated
£1,088
of £1,258
-£170
RH
Ryan Hale
Fitter, crew B, £30/h at cost
32 h
of 32.5 h estimated
£960
of £975
-£15
CW
Callum Webb
Apprentice fitter, crew B, £16/h at cost
24 h
of 23 h estimated
£384
of £368
+£16
True labour cost. The 25 bathrooms finished this year really took 4.5 h per m² tiled, against the old rule of 4.2. This job: 22 m² tiled, priced on 92.5 h. Rule of thumb: 4.2 h per m² tiled. New quotes now use the true rate →
Cost week by week
£8,616 spent over 2 weeks, against a £8,801 estimate
LabourMaterialsSubcontract
Extras and variations · 0
Variations →
No extras on this job.
Timesheets · 88 h, £2,432 at cost
Timesheets →
Week ofPersonHoursCostStatus
17 Aug
Tap for the days
CWCallum Webb24 h
3 days
£384.00
at £16/h
approved
17 Aug
Tap for the days
MTMike Tanner32 h
4 days
£1,088.00
at £34/h
approved
17 Aug
Tap for the days
RHRyan Hale32 h
4 days
£960.00
at £30/h
approved
Purchases · 5, £4,034
Purchases →
OrderWhatStatusNet
PO-5443
Voltmere Electrical Wholesale, raised 14 Aug
Lighting and extractorDelivered 17 Aug, billed£199.75
PO-5444
Avonmere Builders Merchants, raised 14 Aug
Board, tanking and sundriesDelivered 17 Aug, billed£514.95
PO-5439
Kestle Timber, raised 13 Aug
Timber and fixingsDelivered 17 Aug, billed£288.43
PO-5440
Brackwell Tiles, raised 13 Aug
Wall and floor tiles, adhesive, groutDelivered 18 Aug, billed£1,089.32
PO-5425
Linmouth Bathroom Supply, raised 5 Aug
Sanitaryware and brasswareDelivered 14 Aug, billed£1,941.64
Subcontractor invoices · 5, £2,150
Tap one for the subcontractor
InvoiceWorkStatusAmount
SC-3711
Jon Haskins Plumbing and Heating, 20 Aug
Plumbing, second fixPaid£665.00
SC-3712
Gary Pullen Electrical, 20 Aug
Electrics, second fixPaid£195.00
SC-3708
Mark Dent Plastering, 18 Aug
Plastering, skim and making goodPaid£430.00
SC-3705
Jon Haskins Plumbing and Heating, 17 Aug
Plumbing, first fixPaid£665.00
SC-3706
Gary Pullen Electrical, 17 Aug
Electrics, first fixPaid£195.00
Invoices · posted to Xero when sent
Billing →
InvoiceStageStatusNetGrossXero
INV-2386
issued 20 Jul
Deposit
1 line
Paid 5 Aug£2,975.00£3,570.00posted
INV-2410
issued 18 Aug
Progress
1 line
Paid 23 Aug£5,950.00£7,140.00posted
INV-2416
issued 26 Aug
Completion
1 line
Paid 3 Sep£2,975.00£3,570.00posted
Stages £11,900 + billed extras £0 = £11,900 on invoices. £11,900 sent, £11,900 paid.
HC
Henry Cleeve
Henry Cleeve · client since 18 Jun 2026
Site83 Orchard Rise, Portishead
Phone07700 900467
PortalLive: progress, extras, invoices
See what Henry sees in the portal
Messages in the portal
No messages on this job yet.
People and dates
Project managerKate Lyons
CrewCrew B: Mike, Ryan, Callum
Booked18 Jul 2026
StartedMon 17 Aug
Handed over25 Aug 2026
Timeline
Handed over and closed
Kate · 25 Aug 15:00
Jon Haskins Plumbing and Heating: Plumbing, second fix, £665.00
Jon Haskins · 20 Aug 17:00
Gary Pullen Electrical: Electrics, second fix, £195.00
Gary Pullen · 20 Aug 17:00
Mark Dent Plastering: Plastering, skim and making good, £430.00
Mark Dent · 18 Aug 17:00
Jon Haskins Plumbing and Heating: Plumbing, first fix, £665.00
Jon Haskins · 17 Aug 17:00
Gary Pullen Electrical: Electrics, first fix, £195.00
Gary Pullen · 17 Aug 17:00
First day on site: Callum, Mike, Ryan
Site app · 17 Aug 07:30
Booked: £11,900 ex VAT
Owen · 18 Jul 11:00