LIVE DEMO
Kitchen · domestic · fixed price

Job 3963

Complete
Worktops and doors replacement
For Hannah and Patrick Yardley, Bishopston. Chris Moss (small works) with Kate Lyons. On site 18 Feb to 23 Feb, handed over 28 Feb 2026.
Agreed price
£9,000
ex VAT
Final margin
29.0%
quoted 29.7%
100% of the work done9 cabinets
Client's portal view
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
Quoted margin29.7%£2,676 on £9,000
Final margin29.0%£2,613 profit
Invoiced so far£9,000of £9,000, £9,000 paid
Where the money went
PersonHoursLabour costDifference
CM
Chris Moss
Small works and snagging fitter, £30/h at cost
32 h
of 29 h estimated
£960
of £870
+£90
SK
Sam Kerridge
Labourer and driver, £22/h at cost
8 h
of 7 h estimated
£176
of £154
+£22
Rule of thumb: 4 h per cabinet.
Cost week by week
£6,387 spent over 2 weeks, against a £6,324 estimate
LabourMaterialsSubcontract
Extras and variations · 0
Variations →
No extras on this job.
Timesheets · 40 h, £1,136 at cost
Timesheets →
Week ofPersonHoursCostStatus
23 Feb
Tap for the days
CMChris Moss8 h
1 day
£240.00
at £30/h
approved
from the paper sheets
16 Feb
Tap for the days
CMChris Moss24 h
3 days
£720.00
at £30/h
approved
from the paper sheets
16 Feb
Tap for the days
SKSam Kerridge8 h
1 day
£176.00
at £22/h
approved
from the paper sheets
Purchases · 3, £4,651
Purchases →
OrderWhatStatusNet
PO-5181
Avonmere Builders Merchants, raised 15 Feb
SundriesDelivered 18 Feb, billed£227.98
PO-5172
Halbrook Worktops, raised 8 Feb
Worktops, templated and fittedDelivered 20 Feb, billed£2,575.24
PO-5162
Wrenfold Kitchen Supply, raised 4 Feb
Replacement doors and panelsDelivered 18 Feb, billed£1,848.23
Subcontractor invoices · 2, £600
Tap one for the subcontractor
InvoiceWorkStatusAmount
SC-3473
Jon Haskins Plumbing and Heating, 23 Feb
Plumbing, second fixPaid£300.00
SC-3466
Jon Haskins Plumbing and Heating, 18 Feb
Plumbing, first fixPaid£300.00
Invoices · posted to Xero when sent
Billing →
InvoiceStageStatusNetGrossXero
INV-2242
issued 5 Feb
Deposit
1 line
Paid 19 Feb£2,250.00£2,700.00posted
INV-2255
issued 20 Feb
Progress
1 line
Paid 4 Mar£4,500.00£5,400.00posted
INV-2261
issued 2 Mar
Completion
1 line
Paid 7 Mar£2,250.00£2,700.00posted
Stages £9,000 + billed extras £0 = £9,000 on invoices. £9,000 sent, £9,000 paid.
HP
Hannah and Patrick Yardley
Hannah Yardley · client since 20 Dec 2025
Site72 Victoria Walk, Bishopston
Phone07700 900993
PortalLive: progress, extras, invoices
See what Hannah sees in the portal
Messages in the portal
No messages on this job yet.
People and dates
Project managerKate Lyons
CrewChris Moss, small works
Booked3 Feb 2026
StartedWed 18 Feb
Handed over28 Feb 2026
Timeline
Handed over and closed
Kate · 28 Feb 15:00
Jon Haskins Plumbing and Heating: Plumbing, second fix, £300.00
Jon Haskins · 23 Feb 17:00
Jon Haskins Plumbing and Heating: Plumbing, first fix, £300.00
Jon Haskins · 18 Feb 17:00
First day on site: Chris, Sam
Site app · 18 Feb 07:30
Booked: £9,000 ex VAT
Owen · 3 Feb 11:00