Office · commercial · fixed price
Job 3986
CompleteOffice refurbishment
For Fenwick Lane Recruitment, Bristol. Crew C with Gareth Price. On site 12 Jun to 19 Jun, handed over 26 Jun 2026.
Agreed price
£43,100
ex VAT, +£1,150 extras billed
Final margin
20.6%
quoted 19.9%
100% of the work done182 m² floor
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
CostEstimateActual so farFinalDifference
Labour168 h logged against 163 h estimated, at each person's true cost rate£4,486£4,560£4,560+£741.6% overMaterials4 purchases received£17,300£17,251£17,251-£490.3% underSubcontract4 invoices from the electrician, floor layer and plasterer£12,750£13,324£13,324+£5744.5% overTotal cost£34,536£35,135£35,135+£5991.7% overExtras captured on site
1 extra on this job
Quoted margin19.9%£8,564 on £43,100
Final margin20.6%£9,115 profit
Invoiced so far£44,250of £44,250, £42,038 paid, £2,213 retention held
Where the money went
| Person | Hours | Labour cost | Difference |
|---|---|---|---|
DK Dave Kerr Lead fitter, crew C, £35/h at cost | 48 h of 49 h estimated | £1,680 of £1,715 | -£35 |
TA Tom Ashby Joiner, crew C, £30/h at cost | 48 h of 49 h estimated | £1,440 of £1,470 | -£30 |
ER Ellie Rudd Apprentice joiner, crew C, £16/h at cost | 40 h of 36 h estimated | £640 of £576 | +£64 |
RF Rob Finch Decorator, £28/h at cost | 16 h of 14.5 h estimated | £448 of £406 | +£42 |
SK Sam Kerridge Labourer and driver, £22/h at cost | 16 h of 14.5 h estimated | £352 of £319 | +£33 |
True labour cost. The 7 offices finished this year really took 0.95 h per m² of floor, against the old rule of 0.9. This job: 182 m² floor, priced on 163 h. Rule of thumb: 0.9 h per m² of floor. New quotes now use the true rate →
| Estimate line | Estimate | Ordered | Received | Difference |
|---|---|---|---|---|
Partitions, board and ceilings Avonmere Builders Merchants, PO-5335 | £6,230 | £6,124 | £6,124 | -£106 |
Joinery timber and sheet Kestle Timber, PO-5334 | £3,110 | £3,080 | £3,080 | -£30 |
Lighting and electrical Voltmere Electrical Wholesale, PO-5338 | £3,810 | £3,801 | £3,801 | -£9 |
Flooring Cotsmoor Flooring Trade, PO-5344 | £4,150 | £4,246 | £4,246 | +£96 |
Materials count when they are delivered and signed for on site. Nothing is on order and not received. Supplier bills post to Xero from here.
| Trade | Agreed | Invoiced | Difference |
|---|---|---|---|
Electrics and data Andy Rees Electrical, 2 invoices | £7,650 | £7,994 | +£344 |
Plastering Mark Dent Plastering, 1 invoice | £3,190 | £3,334 | +£144 |
Floor laying Nick Weller Flooring, 1 invoice | £1,910 | £1,996 | +£86 |
The forecast counts each trade at its agreed price until it invoices more.
Agreed price
5% retention held on each invoice, stage invoices at 25%, 50% and 25%
£43,100.00
Extras billed
V-3986-1
£1,150.00
Revenue
£44,250.00
Labour
final
- £4,560.00
Materials
final
- £17,250.78
Subcontract
final
- £13,323.75
Profit
20.6% margin, quoted at 19.9% (£8,564)
£9,115.47
Cost week by week
£35,135 spent over 2 weeks, against a £34,536 estimate
LabourMaterialsSubcontract
| Week of | Hours | Labour | Materials | Subcontract | Total |
|---|---|---|---|---|---|
| 8 Jun | 32 h | £824 | £13,005 | £3,997 | £17,826 |
| 15 Jun | 136 h | £3,736 | £4,246 | £9,327 | £17,309 |
Extras and variations · 1
Variations →Timesheets · 168 h, £4,560 at cost
Timesheets →| Week of | Person | Hours | Cost | Status |
|---|---|---|---|---|
| 15 Jun Tap for the days Mon 15 Jun8 hTS-00743 Tue 16 Jun8 hTS-00753 Wed 17 Jun8 hTS-00762 Thu 18 Jun8 hTS-00770 Fri 19 Jun8 hTS-00778 | DKDave Kerr | 40 h 5 days | £1,400.00 at £35/h | approved |
| 15 Jun Tap for the days Mon 15 Jun8 hTS-00744 Tue 16 Jun8 hTS-00754 Thu 18 Jun8 hTS-00771 Fri 19 Jun8 hTS-00779 | EREllie Rudd | 32 h 4 days | £512.00 at £16/h | approved |
| 15 Jun Tap for the days Thu 18 Jun8 hTS-00774 Fri 19 Jun8 hTS-00782 | RFRob Finch | 16 h 2 days | £448.00 at £28/h | approved |
| 15 Jun Tap for the days Mon 15 Jun8 hTS-00749 | SKSam Kerridge | 8 h 1 day | £176.00 at £22/h | approved |
| 15 Jun Tap for the days Mon 15 Jun8 hTS-00751 Tue 16 Jun8 hTS-00760 Wed 17 Jun8 hTS-00768 Thu 18 Jun8 hTS-00776 Fri 19 Jun8 hTS-00784 | TATom Ashby | 40 h 5 days | £1,200.00 at £30/h | approved |
| 8 Jun Tap for the days Fri 12 Jun8 hTS-00736 | DKDave Kerr | 8 h 1 day | £280.00 at £35/h | approved |
| 8 Jun Tap for the days Fri 12 Jun8 hTS-00737 | EREllie Rudd | 8 h 1 day | £128.00 at £16/h | approved |
| 8 Jun Tap for the days Fri 12 Jun8 hTS-00740 | SKSam Kerridge | 8 h 1 day | £176.00 at £22/h | approved |
| 8 Jun Tap for the days Fri 12 Jun8 hTS-00741 | TATom Ashby | 8 h 1 day | £240.00 at £30/h | approved |
Purchases · 4, £17,251
Purchases →| Order | What | Status | Net |
|---|---|---|---|
| PO-5344 Cotsmoor Flooring Trade, raised 11 Jun | Flooring | Delivered 18 Jun, billed | £4,246.13 |
| PO-5338 Voltmere Electrical Wholesale, raised 9 Jun | Lighting and electrical | Delivered 12 Jun, billed | £3,800.52 |
| PO-5334 Kestle Timber, raised 8 Jun | Joinery timber and sheet | Delivered 12 Jun, billed | £3,080.47 |
| PO-5335 Avonmere Builders Merchants, raised 8 Jun | Partitions, board and ceilings | Delivered 11 Jun, billed | £6,123.66 |
Subcontractor invoices · 4, £13,324
Tap one for the subcontractor| Invoice | Work | Status | Amount |
|---|---|---|---|
| SC-3625 Andy Rees Electrical, 19 Jun | Electrics and data, second fix | Paid | £3,997.12 |
Andy Rees ElectricalElectrician, Nailsea. Day rate £280. Insured to Jan 2027. Commercial jobs, data and emergency lighting. | |||
| SC-3626 Nick Weller Flooring, 19 Jun | Floor laying, supply-laid by the floor layer | Paid | £1,995.95 |
Nick Weller FlooringFloor layer, Yate. Day rate £240. Insured to Aug 2027. Commercial vinyl and safety flooring. | |||
| SC-3620 Mark Dent Plastering, 16 Jun | Plastering, skim and making good | Paid | £3,333.55 |
Mark Dent PlasteringPlasterer, Brislington. Day rate £220. Insured to Feb 2027. Skim and dry-lining. | |||
| SC-3614 Andy Rees Electrical, 12 Jun | Electrics and data, first fix | Paid | £3,997.13 |
Andy Rees ElectricalElectrician, Nailsea. Day rate £280. Insured to Jan 2027. Commercial jobs, data and emergency lighting. | |||
Invoices · posted to Xero when sent
Billing →| Invoice | Stage | Status | Net | Gross | Xero |
|---|---|---|---|---|---|
| INV-2316 issued 5 May | Deposit 1 line | Paid 29 May | £10,775.00 | £12,283.50 £539 retention held | posted |
| INV-2351 issued 15 Jun | Progress 1 line | Paid 17 Jul | £21,550.00 | £24,567.00 £1,078 retention held | posted |
| INV-2363 issued 29 Jun | Completion 2 lines, with V-3986-1 | Paid 5 Aug | £11,925.00 | £13,594.50 £596 retention held | posted |
Stages £43,100 + billed extras £1,150 = £44,250 on invoices. £44,250 sent, £42,038 paid, £2,213 retention held until the defects period ends.
Client
Client page →Fenwick Lane Recruitment
Contact: Lucy Lovell · client since 13 Apr 2026
Site70 Gloucester Road, Bristol
Phone0117 496 0551
PortalLive: progress, extras, invoices
Messages in the portal
No messages on this job yet.
People and dates
Project managerGareth Price
CrewCrew C: Dave, Tom, Ellie
Booked3 May 2026
StartedFri 12 Jun
Handed over26 Jun 2026
Retention5% held to the end of defects
Timeline
Handed over and closed
Gareth · 26 Jun 15:00
Andy Rees Electrical: Electrics and data, second fix, £3,997.12
Andy Rees · 19 Jun 17:00
Nick Weller Flooring: Floor laying, supply-laid by the floor layer, £1,995.95
Nick Weller · 19 Jun 17:00
Delivered: Flooring from Cotsmoor Flooring Trade (PO-5344, £4,246.13)
Dave Kerr · 18 Jun 08:15
V-3986-1 approved by the client (portal), £1,150
Client · 16 Jun 19:00
Mark Dent Plastering: Plastering, skim and making good, £3,333.55
Mark Dent · 16 Jun 17:00
Extra captured: Extra power to the kitchenette
Dave · 15 Jun 11:30
Andy Rees Electrical: Electrics and data, first fix, £3,997.13
Andy Rees · 12 Jun 17:00
Delivered: Joinery timber and sheet from Kestle Timber (PO-5334, £3,080.47)
Dave Kerr · 12 Jun 08:15
Delivered: Lighting and electrical from Voltmere Electrical Wholesale (PO-5338, £3,800.52)
Dave Kerr · 12 Jun 08:15
First day on site: Dave, Ellie, Sam, Tom
Site app · 12 Jun 07:30
Delivered: Partitions, board and ceilings from Avonmere Builders Merchants (PO-5335, £6,123.66)
Dave Kerr · 11 Jun 08:15
Booked: £43,100 ex VAT
Owen · 3 May 11:00