LIVE DEMO
Office · commercial · fixed price

Job 3986

Complete
Office refurbishment
For Fenwick Lane Recruitment, Bristol. Crew C with Gareth Price. On site 12 Jun to 19 Jun, handed over 26 Jun 2026.
Agreed price
£43,100
ex VAT, +£1,150 extras billed
Final margin
20.6%
quoted 19.9%
100% of the work done182 m² floor
Client's portal view
Estimate against actual
Live from the timesheets, purchases and subcontractor invoices
Extras captured on site
1 extra on this job
Every extra ↓
Quoted margin19.9%£8,564 on £43,100
Final margin20.6%£9,115 profit
Invoiced so far£44,250of £44,250, £42,038 paid, £2,213 retention held
Where the money went
PersonHoursLabour costDifference
DK
Dave Kerr
Lead fitter, crew C, £35/h at cost
48 h
of 49 h estimated
£1,680
of £1,715
-£35
TA
Tom Ashby
Joiner, crew C, £30/h at cost
48 h
of 49 h estimated
£1,440
of £1,470
-£30
ER
Ellie Rudd
Apprentice joiner, crew C, £16/h at cost
40 h
of 36 h estimated
£640
of £576
+£64
RF
Rob Finch
Decorator, £28/h at cost
16 h
of 14.5 h estimated
£448
of £406
+£42
SK
Sam Kerridge
Labourer and driver, £22/h at cost
16 h
of 14.5 h estimated
£352
of £319
+£33
True labour cost. The 7 offices finished this year really took 0.95 h per m² of floor, against the old rule of 0.9. This job: 182 m² floor, priced on 163 h. Rule of thumb: 0.9 h per m² of floor. New quotes now use the true rate →
Cost week by week
£35,135 spent over 2 weeks, against a £34,536 estimate
LabourMaterialsSubcontract
Extras and variations · 1
Variations →
Timesheets · 168 h, £4,560 at cost
Timesheets →
Week ofPersonHoursCostStatus
15 Jun
Tap for the days
DKDave Kerr40 h
5 days
£1,400.00
at £35/h
approved
15 Jun
Tap for the days
EREllie Rudd32 h
4 days
£512.00
at £16/h
approved
15 Jun
Tap for the days
RFRob Finch16 h
2 days
£448.00
at £28/h
approved
15 Jun
Tap for the days
SKSam Kerridge8 h
1 day
£176.00
at £22/h
approved
15 Jun
Tap for the days
TATom Ashby40 h
5 days
£1,200.00
at £30/h
approved
8 Jun
Tap for the days
DKDave Kerr8 h
1 day
£280.00
at £35/h
approved
8 Jun
Tap for the days
EREllie Rudd8 h
1 day
£128.00
at £16/h
approved
8 Jun
Tap for the days
SKSam Kerridge8 h
1 day
£176.00
at £22/h
approved
8 Jun
Tap for the days
TATom Ashby8 h
1 day
£240.00
at £30/h
approved
Purchases · 4, £17,251
Purchases →
OrderWhatStatusNet
PO-5344
Cotsmoor Flooring Trade, raised 11 Jun
FlooringDelivered 18 Jun, billed£4,246.13
PO-5338
Voltmere Electrical Wholesale, raised 9 Jun
Lighting and electricalDelivered 12 Jun, billed£3,800.52
PO-5334
Kestle Timber, raised 8 Jun
Joinery timber and sheetDelivered 12 Jun, billed£3,080.47
PO-5335
Avonmere Builders Merchants, raised 8 Jun
Partitions, board and ceilingsDelivered 11 Jun, billed£6,123.66
Subcontractor invoices · 4, £13,324
Tap one for the subcontractor
InvoiceWorkStatusAmount
SC-3625
Andy Rees Electrical, 19 Jun
Electrics and data, second fixPaid£3,997.12
SC-3626
Nick Weller Flooring, 19 Jun
Floor laying, supply-laid by the floor layerPaid£1,995.95
SC-3620
Mark Dent Plastering, 16 Jun
Plastering, skim and making goodPaid£3,333.55
SC-3614
Andy Rees Electrical, 12 Jun
Electrics and data, first fixPaid£3,997.13
Invoices · posted to Xero when sent
Billing →
InvoiceStageStatusNetGrossXero
INV-2316
issued 5 May
Deposit
1 line
Paid 29 May£10,775.00£12,283.50
£539 retention held
posted
INV-2351
issued 15 Jun
Progress
1 line
Paid 17 Jul£21,550.00£24,567.00
£1,078 retention held
posted
INV-2363
issued 29 Jun
Completion
2 lines, with V-3986-1
Paid 5 Aug£11,925.00£13,594.50
£596 retention held
posted
Stages £43,100 + billed extras £1,150 = £44,250 on invoices. £44,250 sent, £42,038 paid, £2,213 retention held until the defects period ends.
FL
Fenwick Lane Recruitment
Contact: Lucy Lovell · client since 13 Apr 2026
Site70 Gloucester Road, Bristol
Phone0117 496 0551
PortalLive: progress, extras, invoices
See what Lucy sees in the portal
Messages in the portal
No messages on this job yet.
People and dates
Project managerGareth Price
CrewCrew C: Dave, Tom, Ellie
Booked3 May 2026
StartedFri 12 Jun
Handed over26 Jun 2026
Retention5% held to the end of defects
Timeline
Handed over and closed
Gareth · 26 Jun 15:00
Andy Rees Electrical: Electrics and data, second fix, £3,997.12
Andy Rees · 19 Jun 17:00
Nick Weller Flooring: Floor laying, supply-laid by the floor layer, £1,995.95
Nick Weller · 19 Jun 17:00
Mark Dent Plastering: Plastering, skim and making good, £3,333.55
Mark Dent · 16 Jun 17:00
Andy Rees Electrical: Electrics and data, first fix, £3,997.13
Andy Rees · 12 Jun 17:00
First day on site: Dave, Ellie, Sam, Tom
Site app · 12 Jun 07:30
Booked: £43,100 ex VAT
Owen · 3 May 11:00